The ProfitDig Radio Show
Practical talk for excavation and sitework contractors and estimators. Bid smarter, run the numbers, and keep more of what you earn.
The ProfitDig Radio Show is a straight conversation about the work and the business behind it. We talk through real jobsite situations, estimating and job costing, cash flow, equipment decisions, and the problems that show up when you are running crews and trying to make a profit.
If you dig, estimate, or run a sitework or excavation company, this show is for you. You will hear from the ProfitDig team and from contractors who do this work every day. No fluff. Just practical talk you can use on the next bid or the next job.
New episodes come out every week.
Learn more about ProfitDig, easy job bidding and costing for construction contractors, at https://profitdig.com
If the show helps you, follow it and leave a rating. That is the best way to help other contractors find it.
The ProfitDig Radio Show
How Jobsite Access and Traffic Control can Kill Your Profits
Use Left/Right to seek, Home/End to jump to start or end. Hold shift to jump forward or backward.
Jeff Spencer, Jerry Work and Chris Work discuss how not understanding you jobsite access and any required traffic control can ruin your profits on a construction job. Your employer or general contractor may not explain all of those details.
Https://www.ProfitDig.com - easy, low cost construction job biding, costing and reporting.
So we're rolling.
SPEAKER_01We are. And we were talking about job location. Mm. Alright, we need a how do we go at this?
SPEAKER_00After I open my beer.
SPEAKER_01Okay, that's true.
SPEAKER_00We
SPEAKER_02have one partner that's missing or not. He's on uh uh doing some other work off site, so he won't be present tonight, which is Jeff Gibbons. But uh Jerry, Chris,
SPEAKER_01Jeff,
SPEAKER_02how y'all doing?
SPEAKER_01Well, how are you doing?
SPEAKER_02Doing well, good
SPEAKER_00doing well, doing well, cool. I'm gonna throw this out there too, because this is what these two people do. Okay. Please subscribe or like or leave us a comment, whatever. If you find this content useful and you you like the idea of people like us talking sitting around talking about construction, how to be more successful in construction, then please support us and just like us or follow us or whatever.
SPEAKER_01Um take the bucket of your heavy equipment and smash that like button.
SPEAKER_02As much as you can.
SPEAKER_01Yeah, that's funny. You know, we never ask for likes.
SPEAKER_00We don't really know
SPEAKER_01that. Yeah, yeah, yeah. Which, you know, I mean we we have a decent following on our YouTube channel and and whatnot, um, which is obviously appreciated, but we never ask people to like follow or like us, which is kind of the you know, we're marketing slash construction guys, so that seems a bit ironic.
SPEAKER_02Yeah.
SPEAKER_00You know,
SPEAKER_01you look and learn. Um, you get caught up in in making sure that you offer a killer. I need Azure product, and so yeah. Sometimes
SPEAKER_00it annoys me when you watch a video and they spend so much time just begging you to talk about
SPEAKER_01it.
SPEAKER_00I know, I know.
SPEAKER_01Especially when it's uh scripted, and it's the even somebody you like or someone you like, it's the same thing over and over again, it's kind of comical.
SPEAKER_02Yeah,
SPEAKER_01yeah, yeah. So yeah, so like, follow, um, and all that good stuff. Awesome.
SPEAKER_00All right.
SPEAKER_01I guess we can
SPEAKER_00talk about some
SPEAKER_01you know, yeah. Yeah,
SPEAKER_02yeah.
SPEAKER_01So
SPEAKER_02y'all had some questions for me earlier, you know, about you know, like say proximity of job location?
SPEAKER_01Well, yeah, that's you know, we actually people actually follow and like our content, and we occasionally get questions. Yeah. And one that occurs over and over again is job site stuff. You know, when I I'm going out to bet a job, whatever, uh, I'm new to this, what am I looking for, or is there anything to be learned from just viewing this piece of property that we're about to carve up and and get ready to build on? Um and you
SPEAKER_02yeah, I mean, there's a lot of different you know scenarios you can put together. Uh I know you have a list of questions over there. Uh
SPEAKER_01well I do actually.
SPEAKER_02I'm
SPEAKER_01glad you mentioned it. Well, yeah, because I have a fairly sizable list of questions. Well,
SPEAKER_02and a lot of that derives from, you know, like location, you know, so uh so carry on, ask me a question, see what you see what we get.
SPEAKER_01Okay. Well, I know one of the things that I wanted to ask is um ease of access.
SPEAKER_02Uh well, you know, e ease of access, I mean, it it
SPEAKER_01seems like a no-brainer, but
SPEAKER_02well, it does, but I mean, you know, if you're out in a rural development, you know, of course, ease of access is gonna be easy to obtain. But you know, if you're working somewhere like, you know, here just say here in downtown Dixon or downtown Nashville, you know, it gets congested. So ease of access gets restricted.
SPEAKER_01Yeah.
SPEAKER_02It's like, you know, it's not just so easy to to mobilize. I mean, like, you
unknownknow,
SPEAKER_02I'm not gonna be able to pull into this site and start dropping off equipment or dropping off materials, you know. I I can't get it all done in just say three or four hours' time or a day's time. You know, it's gonna stretch out because you know, you've got to stop traffic, you know, you've got to have ways to unload. If you've got track equipment in your downtown Nashville, if you if you can't fit in your site, you've got to have mats, plywood, tires, other things of that nature, and plus you've got to have labor on staff to be able to go out and put these these things down once your lowboy unhooks to be able to put these things in place to get your piece of equipment or multiple pieces of equipment from the lowboy to the site without damaging the existing asphalt.
SPEAKER_00So it can be a huge difference if you're bidding on job on a job on an acre of land out in the country versus an acre of land.
SPEAKER_02Oh, yes, yes, yeah. Go ahead.
SPEAKER_01I was gonna I want to just put you on the spot for a second. And I know this, I know there's no exact number and it can vary depending on where you're located. But let's just say I I fumble this process in my bed in terms of when can I get in and this and that, and I I way underestimate you know the time involved there. If I'm a small guy, let's say I'm a small guy with a crew, maybe two, my what is it costing me in terms of loss per hour? If I'm if I'm having to wait to get a piece of equipment in, and I've got guys standing around. I mean, I know, you know, and it can be a percentage.
SPEAKER_02Well, it's hard to throw a number at that, but you know, you can a good way to figure it is like it's gonna cost you roughly if you have your own little boy, if you're gonna hire a little boy, whatever it may be, it's gonna cost you roughly around $500 to $600 if you're moving in a 15-20 mile radius to mobilize. Yeah, not a
SPEAKER_01long distance.
SPEAKER_02No, uh to mobilize one piece of equipment. One
SPEAKER_01piece.
SPEAKER_02That's mobilized and demobilized.
SPEAKER_01Yeah.
SPEAKER_02So you're looking at five, six hundred bucks.
SPEAKER_01Yeah.
SPEAKER_02So if you've got a site or a project that's gonna take, you know, four or five pieces of equipment. I mean, you can type, you know, two to three grand pretty easy, you know, just in mobilization, just getting your equipment up.
SPEAKER_01Just kidding,
SPEAKER_00man.
SPEAKER_02Yeah.
SPEAKER_01Yeah.
SPEAKER_02And then if you're like in a restricted area, say you're on 2nd or 3rd Avenue of downtown Nashville, then you're looking at a minimum, you've got to have a flag crew there to stop traffic, direct traffic. You in like Nashville, they require a uniformed police officer to be there to help you direct traffic.
SPEAKER_00Okay, so that's your expense.
SPEAKER_01And so,
SPEAKER_02like with Metro, I've got a contract with Metro. I've got to give them 48 hours' notice of when I need an off-duty police officer with a car to be there on site, and they charge me $50 an hour for the police officer and the car to be there on site, and they got a three-hour minimum, which I don't understand that.
SPEAKER_01Sure.
SPEAKER_02And so, and then at that point, I'm taking plywood, I'm taking tires, blasting mats, whatever I need to lay down to get what's a lowboy drops deck to get that piece of machinery from the lowboy to the job site. So I've got to have a minimum of three to four laborers there to lay this stuff down, pick it up, and move it as each piece of machinery comes in and goes out. So every time you mobilize and demobilize, you know, you're looking at probably, you know, $1,500 to $2,000 in cost by the time you put in your labor per piece.
SPEAKER_01So
SPEAKER_02I mean it can get expensive very quickly. And that's that's one reason you need to look, you know, when you're building a project and make sure that you've got the right number of equipment, pieces of equipment allocated to do this job, and the right personnel on hand, you know, to get this equipment in and out of that project. Sure, you know, a lot of times we like to load up a job site with equipment because it looks good.
SPEAKER_01Sure.
SPEAKER_02But when it's gonna cost you thousands of dollars to move, you know, just say one piece of equipment in and move it out,
SPEAKER_01yeah,
SPEAKER_02you know, you might want to rethink your game, you know, like you know, maybe we need to do this with a minimal amount of equipment.
SPEAKER_01Absolutely.
SPEAKER_02Because it's gonna be a slow-paced job anyway when it's downtown and restricted like it is.
SPEAKER_00Now, if I'm bid if if I'm bidding to a general contractor, is he gonna tell me those kinds of details that I'm gonna need to pay a police officer $50 an hour, or do I need to understand those things?
SPEAKER_02You've got to figure that out because unless you exclude or qualify your bid, like you know, all traffic control, all mobilizations is you know at your expense, not mine, which they're not gonna accept your bid at that point. You know, they're gonna want you to handle your mobilization default. They
SPEAKER_01don't want to deal with that. Right. Yeah.
SPEAKER_02But you know, you need to know when you when you're working in a downtown area, you know, that you're gonna have to acquire, and a lot of times they require a traffic control plan, which that would be at my expense. I've got to produce a traffic control plan. If I've got work that's allocated out in the street, I'm gonna be shutting down multiple lanes. I'm gonna have to produce a plan, an engineer plan to give to this municipality or this uh uh entity to be able to say, yes, we approve or no we don't approve. Because it becomes at that point it becomes a life safety issue. And it's based on like, of course, we call it metro here, but metro fire, metro police department, and metro analyst services. If you've got lane, one lane, multiple lanes, or a whole road shut down, they've got to know because if there's an emergency and that's their ease of access,
SPEAKER_01they've got to
SPEAKER_02reroute. They've got to figure out what the best route for them to go is. So that's why it's so important to know where you're at, and because it's multiple things that can cause you to be at fault. So if if you've got somebody in this apartment complex over here, has nothing to do with the site you're working on, but you blocked their access for the admin service to get there. And there's someone over there having a heart attack or someone's falling or whatever it may be, a fire, then they can't get to there to respond because you haven't done your portion. So they're gonna require you to have a traffic control plant.
SPEAKER_00Alright. What about this? If you're a small contractor here in Dixon County where we're at, you probably don't have to worry too much about traffic control kind of stuff. If I bid a job in downtown Nashville, how do I know that kind of thing like you're talking about? How do I find out those kinds of details that I need to account for to bid that job somewhere like that? That's that's
SPEAKER_02that's something that you need to have a good understanding with the person that you are receiving the invite from.
SPEAKER_00You
SPEAKER_02know, just like I'm a contractor, say you're a general contractor, you send me a bid invite. Well, I look at the location like we know it's possible, I may have to have a traffic control plan. So I'm gonna call you up and say, hey Jay, you know, hey, I appreciate the invite on this job. You know, what are the stipulations for mobilization and demobilization? And and I'm gonna be working out in the streetment portion of this project. What are my requirements? Am I going to have to submit an engineer traffic control plan? Uh, you know, what am I going to have to do on my part? And then at that point, you need to negotiate with whoever you possibly are going to be bidden to. There may be multiple GCs you're bidden to. So don't just take the word of one. You know, you need to reach out to each GC that you're bidden to and find out what they're going to require because this bid for this GC and this bid for this GC may be totally different because of requirements they want you to handle and requirements that they want to handle on their own. And a lot of times you can piggyback off of like your grading contractor or your utility contractor, you know, your paving contractor, they may already have a plan put in place. So a lot of times their plan will work with your plan. So you can contact them, which would be another sub under that GC, and it's like, hey, you know, can you send me your engineer plan, let me use it, because it's going to work with my scope of work.
SPEAKER_01Which this kind of leads into the next question we had about how many trades are on a job site at one time. And depending on the trade that's taking place, you could have a bottleneck with that thing going on. Exactly.
SPEAKER_02And you've got to realize that, you know, you've got to be able to say, you know, you know, if I'm on this site at this particular time, how many trades am I going to be working around?
SPEAKER_01Yeah.
SPEAKER_02That's that's one of the key questions you need to find out or ask yourself, is like, you know, it's going to be a grading contractor, it's going to be a utility contractor, there's going to be a telecommunication contractor, there's going to be a, you know, sooner or later there's going to be a paving contractor there. But most importantly, there's going to be a structural contractor there. The GC. Someone's going to be building this building, whatever it may be, and they're going to have multiple trades there working because their end game is to get this project in, get it into X amount of time frame.
SPEAKER_01Sure.
SPEAKER_02And so, which the more people you have working, or the more trades you have working, the slower your production is.
SPEAKER_01Are GCs very conscious of that? Or have you ever been in a situation where maybe one wasn't so um considerate, I guess, in terms of planning and and strategy?
SPEAKER_02They they are considered, you know, I mean, I mean not considerate, but I mean they have structures in place as far as schedules.
SPEAKER_01Yeah. And so they know that
SPEAKER_02they've got a lot of time for each trade to be in and work together. But like you and I, we may be bidding against each other, and we don't know what that schedule is.
SPEAKER_01True.
SPEAKER_02We we don't see that schedule until it's all over with. And a lot of times their schedule, excuse my French, is just bullshit. You know, the GC puts its schedule together, and like, you know, hey, buddy, how many times have you been on site and actually worked?
SPEAKER_01That's right. You
SPEAKER_02know what I mean? Just because you say I've got this amount of time doesn't mean I can do it in this amount of time.
SPEAKER_01Yeah.
SPEAKER_02And so, you know, that's the end game is from start to finish, your GC has an allotted amount of time.
SPEAKER_01Yeah.
SPEAKER_02So you've got to be able to be up front with them. It's like, you know, I can't do this in that amount of time.
SPEAKER_01Yeah.
SPEAKER_02I can give you X amount of days. Well, they're getting feedback from each contractor. So when they call you and ask you for your amount of time, do not hesitate to be up front with them. It's like, you
unknownknow,
SPEAKER_02my scope of work is going to be X amount of days. You know, based off of everyone else working here, based on location of the job, and based on how hard it's going to be for me to get materials in and out of this project. Because
SPEAKER_01weather.
SPEAKER_02We have weather.
SPEAKER_01And yeah, I guess you have to account for weather. But in general,
SPEAKER_02you know, we do, you know, we do like, you know, we usually like 12 to 15% weather days.
SPEAKER_01Weather days.
SPEAKER_02Yeah, per month. So I mean that that should be just like a common sense thing, you know, it's like it's going to be, you know, 12 to 15% per month.
SPEAKER_01Here. Here.
SPEAKER_02And
SPEAKER_01maybe that could change. It depends on
SPEAKER_02the yeah.
SPEAKER_01It could, depend on location.
SPEAKER_02Yeah, right. But if you can't get in there a lot of time, you know, you need to have a meeting with them, like, you know, hey, I've got X amount of days to do this work. But you as a subcontractor for your scope of work, you've got to be able to recognize job A and job B. This one is downtown restricted. This one's out, you know, in a more less restricted area to where you've got open range and you've got you know pretty good potential of production. This one over here is probably gonna be at 50 to maybe even 100% less production than what you're used to getting. I mean, so you you're gonna have to really slow it down in the bidding process, is where it really comes in, because if you don't want to allocate for those slower days and slower production, then you may get the job because you're low bidder, but you're low because you're way low because you don't have enough time in this job to actually put it in.
SPEAKER_01Right.
SPEAKER_02So, you know, if I'm used to getting, you know, just say a hundred feet a day, you know, water line, seventy feet a day sewer, but I'm on this restructuring restricted site here, I'm lucky if I can get 50 feet a week on one or the other.
SPEAKER_01Wow.
SPEAKER_02Or it may be, you know, grading. You know, maybe it's like I'm used to getting you know a thousand yards a day production. Where over here, I'm having a haul off site, I gotta have flaggers flagging my trucks in and out, haul off site. I'm lucky if I get 200, 250 yards a day.
SPEAKER_01Wow.
SPEAKER_00Alright, let me ask you this. What we're talking about there, like the the congestion in the area you're gonna be working. If I'm looking at an engineer's plans, am I gonna recognize that or do I need to go No,
SPEAKER_02it's not gonna tell you anything on the plans. It's their plans are gonna look just like you know this site over here that's you know 30 miles away out of the rural area.
SPEAKER_00So
SPEAKER_02you've got to be able to recognize, you know, hey, I'm downtown, you know, this is gonna be highly restricted. And you know, and city work, you know, it's actually like three phases to it. You know, you've got your rural rural areas, and you've got your suburb areas to where it's like mediocre, and then you've got your actual downtown areas to where it's like completely restricted. I mean, sometimes it may take you 20, 30 minutes to get one dump truck in and off-site.
SPEAKER_01Oh wow.
SPEAKER_02Yeah. You know, from the time he comes in, gets around all your other trades, gets to the point where he's going, gets loaded, and then gets around other trades and comes back out, you've got a flagger and possible policeman, you know, there to direct traffic. It may be, you know, where typically used to getting a load turned around every three to five minutes, it may take you, you know, a good 15, 20, 25 minutes to get that truck inside, get him loaded, and get him off-site. Maybe even longer than that.
SPEAKER_01Yeah. Substantial.
SPEAKER_02Yeah. There's also, you know, when you've got material, spoiled material, that you're going to need in the future, like as a grading contractor, to finish this job up, you may have a designated area to store it in. But you're still working around other trades. I mean, there's so many scenarios. And then, you know, you've got to store it, well, now it's in a way, now you've got to move it. Well, here it is in a way again, now you've got to move it again. You may handle that material three or four times. So, you know, take that into consideration, and it may be cheaper in the long run to haul that material off site a few blocks down the road or a few miles down the road and stockpile it and then move it back in instead of moving it multiple times.
SPEAKER_01Well, here's another one, Corey. All these trucks coming and going create a lot of noise.
SPEAKER_02It does.
SPEAKER_01Heavy equipment.
SPEAKER_00I think we should save that for the next episode.
SPEAKER_01The next episode?
SPEAKER_00Yes.
SPEAKER_01Okay.
SPEAKER_00I think we'll
SPEAKER_01do that.
SPEAKER_00This is this is part one of this discussion. And we will pick it up shortly. Keep
SPEAKER_02it on the book, Chris.
SPEAKER_01We'd like to keep you on the edge of your teeth as much as well.
SPEAKER_00So once again, please subscribe and follow and like hit
SPEAKER_02that like button
SPEAKER_01like button.
SPEAKER_02Yeah.
SPEAKER_01Um, comment, ask questions, we would love that. Um at infoprofitdig.com. Whatever we can do to help.
SPEAKER_00And if you you know could use a low-cost, high-quality construction job, bidding, and costing solution, please visit us at profitdig.com. Starts at 99 bucks a month. You can run your whole company on it.
SPEAKER_01Yeah, it's kind of crazy, actually. Yeah, very cool. Awesome. All
SPEAKER_00right,
SPEAKER_02so no contract either.
SPEAKER_01Oh, no contract. I don't like contract. I don't like the work on that. No,
SPEAKER_00no contract.
SPEAKER_01No, I think.