Practical talk for excavation and sitework contractors and estimators. Bid smarter, run the numbers, and keep more of what you earn.
The ProfitDig Radio Show is a straight conversation about the work and the business behind it. We talk through real jobsite situations, estimating and job costing, cash flow, equipment decisions, and the problems that show up when you are running crews and trying to make a profit.
If you dig, estimate, or run a sitework or excavation company, this show is for you. You will hear from the ProfitDig team and from contractors who do this work every day. No fluff. Just practical talk you can use on the next bid or the next job.
New episodes come out every week.
Learn more about ProfitDig, easy job bidding and costing for construction contractors, at https://profitdig.com
If the show helps you, follow it and leave a rating. That is the best way to help other contractors find it.
How Bad Engineers Cost a Project Owner Money: The ProfitDig Radio Show Episode 13
•ProfitDig LLC
Use Left/Right to seek, Home/End to jump to start or end. Hold shift to jump forward or backward.
0:00
|
10:26
In this "Jeff and Jeff" episode of the ProfitDig Radio Show podcast edition, project manager Jeff Spencer talks about the problems he has had dealing with engineers with little field experience, how bad engineering results in change orders, who is responsible for change orders that result from engineering mistakes and more.
This is valuable information for project managers, contractors or anyone involved in the field of construction. Subscribe to the ProfitDig Radio Show podcast to learn about building and running a successful construction business.
SPEAKER_01
This is the profit living video, so don't let us down.
SPEAKER_02
This is the profit living video. Radio Show with Jeff and Jeff.
unknown
No, I
SPEAKER_03
don't know. Alright, so Just Spencer, what are some common engineering challenges that you face on different construction job sites?
SPEAKER_04
Well, there's a that's a pretty broad aspect. Uh and I'm gonna back up a little bit, you know, for for several years now I've said that if you're gonna be an engineer and a civil engineer and design construction sites, you should have to spend a minimum of five years working in the field before you design one. And case in point is like, you know, you have several jobs you're doing throughout the year and it never fails. You got issues that doesn't work. You go to the engineer and you talk about it, and they're like, well, you know what they show you on paper how it works, but it doesn't work in the field, and then and and there's a disconnect there between the contractor and the engineer, because a lot of times you can't make the engineer understand why he may be at fault or he's designed something that doesn't work, but he's not going to take responsibility for it. You know, in his mind, he's given you something good that's good to work by, and 90% of the job may work according to his design, but there'd be one item that just may not work, you know, just because it's not designed the way it should be.
SPEAKER_03
Is that because they're not receptive to the fact that they don't want to listen to you? Maybe they don't they don't think that you're capable of describing those issues, or maybe they have they're too busy to bother themselves with
SPEAKER_04
the other. No, I think it's just it's not really ignorance, but it's ignorance to the point of not laying hands on it, you know, not being in the field and getting a physical experience to see, you know, why these issues, you know, may be something they could do different if they understood what it looked like in the in the real world. And it's tough to get an engineer on site a lot of times to, and the engineer itself, if you if you request a site visit, nine times out of ten, they're going to send someone else out that's under them. You know, they're they're physically not going to make that that visit theirself. And as time goes on, you see it more and more because the guys that go to school that get educated to be an engineer and they start design right off the bat, and they never have anything as far as a real scenario to see how a job actually goes in that they're actually designing.
SPEAKER_03
Do you have any control over the engineers that are responsible for those sites? Or
SPEAKER_04
no. So
SPEAKER_03
you're just at the mercy of whatever hand you're belt.
SPEAKER_04
Well, it's it's it's a kind of a catch-22 because the owner or whoever you may be working for, it may be a municipality, it may be a GC, it may be, you know, whoever's flipping a bill for this, they're the ones going to incur the cost. The engineers got a set rate. They get a design rate and then they get a percentage rate based off of what the monetary amount of that project is to oversee that project and make changes. So we do what we call change orders. When something doesn't work in a field because of poor design or something that was missed in the design phases, the owner has to flip that bill. And in my opinion, it shouldn't always be on them. If it's a poor design or the engineers didn't look at it, or architects didn't look at it, you know, correctly, they're never at fault. But the owner has to eat the cost to make those changes. And every every contractor is the same way. When you bid a job, you've got a certain amount of overhead and and profit figured in this project. When it comes to change orders, you inflate those rates because it's aggravation to you and to your company and your employees to have to go back and do your job two or three times to make this one item or multiple items, you know, work out.
SPEAKER_03
Do they have the opportunity to deny those change orders?
SPEAKER_04
Yes, they do. But there again, you know, you're back in th they don't really deny the change orders, they have the opportunity to uh deny the the monetary amount. Because the change orders are coming about because it will not work based off the design.
SPEAKER_03
They're beholden or at least required to at least meet the minimum specs in that job.
SPEAKER_04
And the way I look at it is, you know, if if they want to bucket my price and don't agree with it, they've got every right in the world to hire somebody else to come in. But nine times out of ten, they're not going to seek that route because you're already on site, you're under contract, you're doing the work, so most of the time they they're going to have to uh meet your your conditions to get the work done.
SPEAKER_03
Is that engineer usually assigned by the general contractor on the job or the the architect?
SPEAKER_04
Well, it depends on how the the job is structured, you know, as far as from the owner through the architect to through the engineer. Uh they kind of delineate, you know, who's in charge and who makes those decisions, but ultimately it goes back to the the owner, you know, whoever is is paying for this project, they're the ones going to incur the cost.
SPEAKER_03
Do you have any sort of system of determining like this is an engineer that I like to work with, like just history with them, or oh yeah, I
SPEAKER_04
mean, sure. You know, there's there's always uh there's a lot of engineers out there that I I prefer to work with, and there's a lot of engineers out there when I see a set of their drawings or blueprints come across my table, I dread it right off the bat. If I get this job, I know it's gonna be a hassle most of the time.
SPEAKER_03
Do you try to inflate your margins like just to account for that?
SPEAKER_04
Uh no, not really, because it's a competitive market. I'm bidding against other people, so I've got to stay competitive. Uh but I know that there's uh really good potential for change orders to come about, and which theoretically usually means more profit in my pocket.
SPEAKER_03
You ever had a job where you haven't had a change order?
SPEAKER_04
Yes. Yeah, I've had jobs, you know, I've even had you know large-scale jobs start to finish, go all the way through, and no change orders, everything worked like it's supposed to. And then I've had some small jobs that should be pretty simple and have six, seven, eight change orders on that one project. You know, a project may be, you know, $200,000, $250,000 on my scope of work, end up being, you know, $350,000, $400,000 based off change orders.
SPEAKER_03
Is there any sort of penalty for having a certain amount of change orders on a project? Well,
SPEAKER_04
I'm not for sure. Right, you know, I'm not for sure about that. You know, if it is penalties, it it goes on above me in my scope of work because I'm contracted out to do X amount of dollars for this scope of work. And when things don't work like they're supposed to, and we have to make changes, then someone has to incur those costs and approve them, and and so I I never see that. You know, either I get approval and get a signed change order back or they redesign, and and if my monetary amount is too much, then they may look at another redesign and try to figure out something else. Which there again, you've got an owner that has a deadline to get this project in. These designs take a time. These change orders take time to get designed and get approved. So you're delaying that project uh and which most of the time you have liquidated damages on most projects, so they get pushback for the most part. Uh but uh a lot of times it's not enough time. You know, they give you an extra 30 days. Well, it took 30 days to design. Well, here we are, we got you know 30 days more worth of work, but our 30 days are used up through the design phases.
SPEAKER_03
What do you do in a situation like that?
SPEAKER_04
Well uh it's kind of a they're again kind of a catch-22. Depends on who your owner is and who your engineer is. A lot of times you may go over your time limit and they may bypass the liquidate damage, they may not charge you because they know it's their fault, you know it's been in design stages and and it was withheld, you know, out out of out of your control. Uh and then you throw weather days on top of that. You know, once a once a building or a project is dried in, you know, weather is kind of irrelevant, you know, for the most part. But when you're doing grade work and utility work, weather pays a plays a big uh percentage in in what work you can get done. If you've got a lot of bad weather, then you're gonna have weather delays. So and a lot of times, you know, they'll give you a certain percentage, you
unknown
know,
SPEAKER_04
10 or 15 percent, you know, for weather delays, but you take changes on changes and plus weather, you know, it it it outweighs that by a great great deal. So it must
SPEAKER_03
affect in your backlog too, right? Yeah.
SPEAKER_04
Because you know, you've got deadlines and then you you got schedule to move on this other new project, you know, at a certain date, but you can't do it because your crew's tied up on a existing job because of changes. Well guys, we just wanted to give y'all a little heads up. You know, there is some stuff, you know, that you can uh uh run into, you know, as far as design, you know, just because you got an engineer or engineering firm, it doesn't also mean that they're gonna have every answer, you know, to that project. You know, there's gonna be changes that have to be made, and they're not always right. You know, they're they're they don't have the the experience, you know, a lot of times in the field and and can't really foresee how a job's gonna go in. It looks good on paper, but it doesn't always look good in in real life. But anyway, just want to give you all a little heads up on that. And uh we got Jeff G here with us tonight, our fourth partner. He's not always with us, and we're glad to have him and uh hope to see him more in the future.