Practical talk for excavation and sitework contractors and estimators. Bid smarter, run the numbers, and keep more of what you earn.
The ProfitDig Radio Show is a straight conversation about the work and the business behind it. We talk through real jobsite situations, estimating and job costing, cash flow, equipment decisions, and the problems that show up when you are running crews and trying to make a profit.
If you dig, estimate, or run a sitework or excavation company, this show is for you. You will hear from the ProfitDig team and from contractors who do this work every day. No fluff. Just practical talk you can use on the next bid or the next job.
New episodes come out every week.
Learn more about ProfitDig, easy job bidding and costing for construction contractors, at https://profitdig.com
If the show helps you, follow it and leave a rating. That is the best way to help other contractors find it.
Why Field Experience is So Critical to Being a Successful Project Manager: the ProfitDig Radio Show Episode 9
•ProfitDig LLC•Season 1•Episode 9
Use Left/Right to seek, Home/End to jump to start or end. Hold shift to jump forward or backward.
0:00
|
4:26
In this episode, Jeff Spencer talks about the time he had major conflict on a job that required change orders because a sewer manhole that the project required tying into was far too close to a foundational wall. Following the original plans could have been disastrous or far more expensive. Jeff recognized the need for change when we saw the jobsite with his own eyes and had to explain to the engineers why their plan would not work.
Jeff recommends that all estimators, project managers and engineers have multiple years of hands-on experience in the field.
SPEAKER_00
It's the Prophet Dig Radio.
SPEAKER_01
Hey guys, Chris Wark and Jeff Spencer at Profit Dig. Jeff, we were talking earlier. Um, you were telling us the story of uh one time on a job side and has had uh issues a bit of inexperience, and I thought, gosh, this is such a great story and a lesson for anyone in the business that thought we should share. And it's basically why it's so important for any estimator or project manager to have adequate field experience.
SPEAKER_02
Yeah. Yeah, we've we've talked about it in the past, you know, in other videos and stuff, but uh I think it's a good rule of thumb, you know, all estimators, project managers, and even engineers, you know, should have a minimum of four or five years hands-on experience in the field, you know, actually doing work. Uh the particular project you're talking about, we were working in Nashville and we were working on a hotel project, and uh there was a sewer manhole that we were supposed to tie into. During the bidding process, everybody bid the job and tie in this manhole. Well, when you get on site and actually see the manhole in relation to the structure, this was an existing structure that was being reworked, uh, the manhole was probably seven, eight feet off of the building wall.
SPEAKER_01
Oh wow.
SPEAKER_02
Yeah. And there was a partial basement under this building, but uh it was the foundation itself was only about ten feet deep. This particular manhole was a little over 17 feet deep. We had to tie in inward elevation. So we had to dig a hole, you know, roughly have roughly four or five feet around the manhole to be able to have access to do our work. And it being as close to the building as it was, there was no way that we could, you know, excavate that that manhole without jeopardizing the structure of the building. And the project manager on this particular site and the engineer, we had meetings on site, and uh they were just couldn't understand why it was a structural issue. You know, it worked on paper.
SPEAKER_01
Right.
SPEAKER_02
So if it worked on paper, it should work in the field. And I I had to go in and redesign the sewer and show them how it would work by tying in to a different location. Uh, of course, I got some controversy and conflict back because it was going to be a change order. It was going to be a little more cost, but nothing as severe as the cost would have been to try to uh drive pilings that close to a building and try to secure the the banks and stop anything, any kind of cave-in or structural damage. And uh it was just gonna be a nightmare.
SPEAKER_01
OSHA probably likes that too.
SPEAKER_02
Yeah, they probably wouldn't. Uh but it was uh it was an ordeal. Uh it took a few weeks to get it worked out and ironed out, but uh the engineers uh of record that was on the project, the engineer that was doing it, went back and talked to the the I guess his boss or whoever it might have been over him, and he agreed with my concerns and and liked the design I had proposed.
SPEAKER_01
Right.
SPEAKER_02
So
SPEAKER_01
you're able to move forward.
SPEAKER_02
We were able to move forward. He he incorporated design into his uh uh documents and put out a ASI and we got it changed and was able to do it in a safe and timely manner. And
SPEAKER_01
yeah,
SPEAKER_02
uh, but it wasn't by no means a way for us to generate more money or change, or it was just trying to avoid something that could be detrimental to the job site and people or the structural of the building itself.
SPEAKER_01
Yeah, absolutely.
SPEAKER_02
But just because someone has a title doesn't necessarily mean they have the experience needed to be in that position.
SPEAKER_01
Yeah. So guys, get out in the field and spend your ad spend your time there and actually figure out how all this works before we start putting a pencil and paper. Alright, Jeff. Alright,