Practical talk for excavation and sitework contractors and estimators. Bid smarter, run the numbers, and keep more of what you earn.
The ProfitDig Radio Show is a straight conversation about the work and the business behind it. We talk through real jobsite situations, estimating and job costing, cash flow, equipment decisions, and the problems that show up when you are running crews and trying to make a profit.
If you dig, estimate, or run a sitework or excavation company, this show is for you. You will hear from the ProfitDig team and from contractors who do this work every day. No fluff. Just practical talk you can use on the next bid or the next job.
New episodes come out every week.
Learn more about ProfitDig, easy job bidding and costing for construction contractors, at https://profitdig.com
If the show helps you, follow it and leave a rating. That is the best way to help other contractors find it.
The ProfitDig Radio Show Episode 3: What's It Like Being a Project Manager?
•ProfitDig LLC•Season 1•Episode 3
Use Left/Right to seek, Home/End to jump to start or end. Hold shift to jump forward or backward.
0:00
|
8:48
In the third episode of the ProfitDig Radio Show, Chris Work asks Jeff Spencer about the things he typically has to deal with as a project manager and estimator.
Jeff also gets attacked by a microphone.
From ProfitDig - the world's easiest to use construction job bidding, costing & reporting solution.
As what I do, I'm an estimator and a project manager. So when I bid a project and I generate my cost for that project, I send a bid in, and then I'm a you know, if lucky, I'm awarded that bid. Well, at that point, I have to manage that job to make sure it comes in at or below budget. That's my goal, is to come in below budget. Sure.
SPEAKER_01
It's the Profit Day Radio Show.
SPEAKER_02
We good? Alright. Take two. Take two. Take two. It's not like a blooper's reel, maybe.
SPEAKER_00
Yeah.
SPEAKER_02
You know? We don't have a profit day.
SPEAKER_00
We could probably put them together though.
SPEAKER_02
Does that mean all of our videos would be included in the movie?
SPEAKER_00
Yeah. Yeah.
SPEAKER_02
Yeah. Well, that's how we're gonna start this one anyway.
SPEAKER_00
Alright.
SPEAKER_02
Jeff, it's cold outside.
SPEAKER_00
It is.
SPEAKER_02
Yeah, it's a cold January night here in Tennessee.
SPEAKER_00
Sure enough.
SPEAKER_02
I was just saying earlier, you like the cold.
SPEAKER_00
I do.
SPEAKER_02
See, I could go to sleep in October and wake up in April and be just fine.
SPEAKER_00
Well. In
SPEAKER_02
fact, I I'm I think bears already they they figured that
SPEAKER_00
out. I wouldn't I wouldn't mind seeing your six plus inches of snow in ground now.
SPEAKER_02
All right. I do enjoy the snow.
SPEAKER_00
Yeah.
SPEAKER_02
Yeah. But I don't want the rainy cold weather. So anyway, enough about our weather here. Jeff, something I've been meaning to ask you, and I think would be useful for our viewers.
SPEAKER_00
Alright.
SPEAKER_02
What is it like in the day of a project manager?
SPEAKER_00
Well, Jerry and I was talking earlier before we came to a meeting.
SPEAKER_02
It is good for the bloopers.
SPEAKER_00
But uh
SPEAKER_02
Jeff.
SPEAKER_03
I'll engineer this a little bit. I'm gonna pull this back.
SPEAKER_02
Uh testing one, two, three.
SPEAKER_00
Testing one, two, three.
SPEAKER_02
A day in the life of a project manager, Jeff.
SPEAKER_00
Just like earlier today, Chris. I mean, uh, Jerry and I were talking, you know, and it's uh always bids coming in. You gotta get bids out.
SPEAKER_02
Right.
SPEAKER_00
But, you know, then you have other stuff come in that that has to take priority.
SPEAKER_02
Sure.
SPEAKER_00
Uh, you know, for instance, yesterday and today both, I had calls come in for jobs that most of them were, or both of them are budget prices, but they had to be returned by the end of the day. So I had to put my my normal bids on hold to work on these particular two jobs to get them out, you know, in a in a speedy fashion.
SPEAKER_02
Yeah.
SPEAKER_00
But, you know, as what I do, I'm an estimator and a project manager. So when I bid a project and I generate my cost for that project, I send a bid in, and then I'm gonna, you know, if lucky, I'm gonna award that bid. Well, at that point, I have to manage that job to make sure it comes in at or below budget. That's my goal, is to come in below budget.
SPEAKER_02
Sure.
SPEAKER_00
At budget is good, you know. I mean, that's that's what you bid a job for.
SPEAKER_02
Sure.
SPEAKER_00
But I always try to find ways, you know, to cheapen up that job to to make it come in under budget. Because that's more profit for the guy I work for, and you know, more profit for me in the in the in the end game.
SPEAKER_02
Right.
SPEAKER_00
Uh but you know, there's a lot of ways to do it. Uh every job is different. You have similar jobs, but every job is different. You know, some jobs you can put in in a in a speedy amount of time, some jobs, you know, like in your downtown areas, you know, they're they're long and drawn out. Um, but basically the only way you can do it is by production. If you can find ways here and there, you know, to stuff the engineer or architect may have missed.
SPEAKER_02
Sure.
SPEAKER_00
Uh, you know, you can do some stuff, uh do some value engineering. Um in a budget stage, you know, you've got to you gotta relay that back and forth with the contractor or the owner that you're working with. But when you're awarded a job, then if you can do some value engineering, there's a chance you can keep that money in-house. So if you pick up an extra two, three, four percent, then you know that's that's just that much more money you can possibly make
unknown
uh
SPEAKER_00
in the long run. But you know, that's just stuff you gotta look for. You gotta find ways to be able to speed up a job to decrease your your production, or increase your production rather.
SPEAKER_02
Right. I was gonna ask you about that. Yeah, yeah.
SPEAKER_00
Increase your production to to lower your production cost, to decrease your production cost. Uh because you and I are being against each other, and my materials, your materials, they're gonna be basically the same amount.
SPEAKER_02
Sure.
SPEAKER_00
I mean, they may be within one or two percent at the most.
SPEAKER_02
Yeah.
SPEAKER_00
But when I look at a project, I see a certain time frame that I know my guys and stuff can put it in, and therefore you do the same thing with your guys. You're like, you know, you I think my guys can get this amount of footage per day, this amount of cubic yards per day. You know, whatever you may be into uh as far as your field of expertise, uh you see ways that you can speed up a job.
SPEAKER_02
Right.
SPEAKER_00
So I always go into a project when I'm bidding it as a as conservative as possible, and then once I'm awarded that project, then I try to get it as aggressive as possible.
SPEAKER_02
I have a question. Talking about how you know or you have a pretty good idea of how efficient a particular your crew is, or you know, what have you in terms of estimating how long it's gonna take or how much production you can get? Let's say uh two guys on a small crew that's been with you a long time, they take off and they start their own gig. And then you're you're bringing in some new guys. Let's say you don't know a lot about how efficient they might be. Does that impact or change the way you bid a job?
SPEAKER_00
Well, not necessarily, because you know, we've got multiple crews, and I try to take an average.
SPEAKER_02
Sure, but
SPEAKER_00
between the crews. Okay, but I cannot take into account a new crew coming in or old crew taking because I never know what crew is gonna be available for that project once I'm awarded.
SPEAKER_02
Right.
SPEAKER_00
So if we use a guideline, you know, take an average of what your your crews normally do, then at that point, you know, it's it's gonna be if I send this crew out there and they're not as productive as the crew I hope for, I may not make as much money as I hope for, but if they are a mediocre crew and can get to you know a good production on a daily basis, then nine times out of ten, you're gonna come out alright. You know, you're still gonna be at budget or even you know, maybe a little below budget.
SPEAKER_02
One thing that might slow a crew down, is that an operator? Would that be at the top of the list?
SPEAKER_00
Well, it could be an operator, it could be a a foreman.
SPEAKER_02
Okay. You
SPEAKER_00
know, your foreman, you know, it's it's he's he's your leader on that project.
SPEAKER_02
Right.
SPEAKER_00
And so how he manipulates that job or how he uh uh coordinates that job can be either efficient or not efficient.
SPEAKER_02
Sure.
SPEAKER_00
So, you know, he's gotta be thinking from boots on the ground to where he wants to be at the end of the day every day. And you know, it's like my dad told me, you know, when I leave a job every day, I need to be thinking about what I'm gonna be doing the next day. You know, I don't need to be, you know, making friends with the crew I'm with or anything else, you know, riding down the road, worrying about drinking a beer or whatever.
SPEAKER_02
You know,
SPEAKER_00
I need to be focused on tomorrow because that's my train of thought. At the end of the day, I've got to, at the end of the day, I've got to figure out what that job needs to look like when I leave and where my start point's gonna be the next day when I get back.
SPEAKER_02
Yeah, and you're gonna be you'll be showing up the next day and cleaning up and moving stuff around. So it makes sense. Well, Jeff, I appreciate you sharing that. Yeah,