The ProfitDig Radio Show is a straight conversation about the work and the business behind it. We talk through real jobsite situations, estimating and job costing, cash flow, equipment decisions, and the problems that show up when you are running crews and trying to make a profit.
If you dig, estimate, or run a sitework or excavation company, this show is for you. You will hear from the ProfitDig team and from contractors who do this work every day. No fluff. Just practical talk you can use on the next bid or the next job.
New episodes come out every week.
Learn more about ProfitDig, easy job bidding and costing for construction contractors, at https://profitdig.com
If the show helps you, follow it and leave a rating. That is the best way to help other contractors find it.
The ProfitDig Radio Show
Rain Days Killing Your Schedule? Here’s How Pros Handle It
Use Left/Right to seek, Home/End to jump to start or end. Hold shift to jump forward or backward.
Rain can shut a site down fast - muddy ground, unsafe conditions, blown timelines. Jeff breaks down how real contractors keep crews productive, protect their budgets, and avoid getting hammered with liquidated damages.
From prefab work under tents to smart job selection to documenting every weather delay (and getting signatures to back it up), this is how you survive the wet season without blowing your margins.
If you want tighter records, cleaner reporting, and a bidding tool that keeps your numbers straight even in the messy seasons, check out ProfitDig. No contract. Risk-free. 30-day money-back guarantee.
https://ProfitDig.com
Well why did this job get upside down?
SPEAKER_01You know,
SPEAKER_02you know, is that something you guys prepare for?
SPEAKER_01I don't want to give up profit. What I do is I speed up the
SPEAKER_02welcome to Profit Dig Live. I'm Jeff Givens. I'm here with Christopher Ward. Jeff Spencer.
SPEAKER_01Hey guys.
SPEAKER_02And as always, producer Jerry behind the camera. So Jerry.
SPEAKER_01Hello.
SPEAKER_02Hey, guys, can we talk about rain?
SPEAKER_00Oh,
SPEAKER_01we got plenty to talk about, don't we?
SPEAKER_02Yeah, it's raining right now. Like forest gump, levels of rain. It's not that bad.
SPEAKER_00No. But it's it's been constant.
SPEAKER_02It has been. We had a drought for a while. It was really dry and dusty. Now it's just raining constantly. So I guess what do you do with your crew, with your company, when you're in a s in a season of rain?
SPEAKER_00Yeah. Well, I guess you can't just send them home and say, sorry, guys can't pay you. I mean, you may have to do that to some folks, I guess. I don't know, but
SPEAKER_01well, yeah, you know, unfortunately you do a lot of times. And we we try to, of course, we know that this time of year and going into spring, you know, winter and spring both is a wet season for us here in Middle Tennessee. So we we generally try to plan ahead and kind of try to, when you got plenty of work, you can do this. If you don't have plenty of work, it's tough to do. But we try to be selective on the areas that we're going to be working in, you know, or been work in in the wintertime to try to find rock jobs where we got shot rock.
SPEAKER_00Now,
SPEAKER_01you know, we don't expect our guys to work and pour down rain, you know, but if it has rained a few days, uh, and even with the light rain, they'll still work as long as they're on rock, you know, or maybe a street job. You know, if you're working in the street somewhere and you got traffic shut down or uh narrowed down to one lane or two lanes or something like that, you know, where your guys can work without making too much of a mess. So that's what we generally try to do. But it doesn't always work out. Right now, you know, we just happen to have some jobs that was delayed getting started, and they started later than than we anticipated. And we've actually got some guys working on some pretty decent dirt jobs. And so they have been inhabitable for the last two or three days.
SPEAKER_00Yeah.
SPEAKER_01So what we've had to do, you know, I mean, we we try to generate jobs for our guys. Short term you can do that, but long term it really gets into your budget because they got to charge their time
SPEAKER_02to
SPEAKER_01something, you know, so it's got to be charged a job to cost after time. So you got to really watch how you do that, you know, because you can bust your budget pretty quickly. You know, if you got two or three weeks worth of time there's really wet and you got your guys in, you know, around the shop, you know, straightening up, you know, cleaning up, putting up fence or you know, organizing fittings or, you know, stuff of that sort. And
SPEAKER_00we've good.
SPEAKER_01Right.
SPEAKER_00I mean, down the road, when you look back, it'd be like, Why why did this job get upside down for a period of time?
SPEAKER_01Yeah.
SPEAKER_00Yeah.
SPEAKER_01We had the guys in here, you know, doing this, doing that, and had a charger time somewhere. And also, you know, like I mean, if it's a utility job, and so you got some water lines and stuff of that nature, uh, what we call like three ways, you know, like you got a T and you got a valve on each side of the T, you may have that happen multiple times throughout a job.
SPEAKER_02Or
SPEAKER_01you got a fire hutter, and your fire hunting has to have a valve on it. So, what we'll do a lot of times is we'll set up a couple tents on the job site, have that material sitting there, and have some guys go out and start putting those together. That way they're pre-fabbed.
SPEAKER_02Yeah.
SPEAKER_01Then when you get to them, you know, so you can actually charge your time to the job. You got your guys working, and you're not creating too big of a mess.
SPEAKER_00Yeah.
SPEAKER_01Uh, and that way they can do something productive for that job. That way it's not not considered a waste of time. They gotta do it sometime or another.
SPEAKER_00Sure.
SPEAKER_02Yeah, I was gonna ask about what sort of tools or equipment could you put on. So you mentioned a tent. Um, but even in the rain, I guess, like, you know, is that something you guys prepare for? Uh that you have each crew has a tent.
SPEAKER_01No, no, they come to the shop and get a tent, you know, and we have them at the shop. Uh there again, you know, it's still not gonna alleviate the mud, but if it is raining, they can at least work and stay dry. And you've only got like one piece of equipment that may have an excavator or a loader that's bringing materials to them to put together so you know you're not generating too too big of a muddy area, you know, to
SPEAKER_00to
SPEAKER_01work in. Just
SPEAKER_02respecting the landscape when you're working on it.
SPEAKER_01Yeah,
SPEAKER_00yeah.
SPEAKER_02Yeah. And then when you're preparing for, you know, especially different rainy seasons, you know, I mean you never know, right, when it's gonna be. But there are common times of the year that are rainier than others, that are wetter than others. Uh, do you use any sort of predictive tools, like I don't know, even something like a farmer's almanac or anything like that?
SPEAKER_01No, I mean, we don't. I mean, there may be some people out there that do. You know, we just try to watch, you know, extended forecast.
SPEAKER_02You know,
SPEAKER_01get a seven to ten day forecast, which about 85% of the time you can't depend on those either.
SPEAKER_02Well, that doesn't really help you when you're bidding the job. No,
SPEAKER_01it doesn't. But we know in general, you know, like generally uh June and July, more like July and August are gonna be relatively dry.
SPEAKER_00Yeah.
SPEAKER_01Usually October is our driest month of the year. You know, you can just about bet going all October,
SPEAKER_02really,
SPEAKER_01you know, without just maybe one or two rains.
SPEAKER_00Yeah.
SPEAKER_01Uh
SPEAKER_02and that's relative to our region. Our
SPEAKER_01region.
SPEAKER_02Our region. Yeah.
SPEAKER_01But we know that November, December, January, February, March, even into April, that's our wet season. That's what we consider our wet season. So we try to look at jobs that are going to be bidding, you know, that are going to be in areas where you know you've got a higher content of high rock, you know, or or or or outcrops of rock. So you know there's going to be blasting, you know, there's going to be rock fuel put in, the overburden's going to be stripped off. You it's going to be a solid rock job, so you're going to have rock from one side to the other for the most part. So yeah, you know, your guys are not going to work in a pouring down rain, but they don't have to worry about mud. As soon as the rain stops, they can go to work, no, no harm, no foul. But those jobs aren't always available to bid, you know, those regions you know I'm talking about may not have, you know, a whole lot of work going on at that
SPEAKER_02time.
SPEAKER_01But you know, you've got to strategically try to look at you know the areas when you're bidding work, like, hey, I'm gonna go after this one hard. It's gonna start, you know, in late November, early December, and I can keep our guys busy for three months there, you know, working on shot rock.
SPEAKER_00Yeah. Do you ever reduce your fingers on a job like that? Yeah, depending just give me a better shot of getting this.
SPEAKER_01If if I've got a projected start date.
SPEAKER_00If you have a projected start date.
SPEAKER_01If I know for sure it's gonna start, you know, somewhere in that wet season,
SPEAKER_00yeah,
SPEAKER_01then you know I will.
SPEAKER_00You're willing to give up some profit. I'm willing
SPEAKER_01to, you know, I don't really give up profit. What I do is I speed up production.
SPEAKER_00Okay. All right. Yeah. Okay. And uh,
SPEAKER_01you know, that way on paper, you know, my profit stuff is always in there.
SPEAKER_00Okay.
SPEAKER_01But I still try to keep it in reach of the guys, you know, it's something that I know if they really bust their ass, this is a target they can achieve.
SPEAKER_00Yeah.
SPEAKER_01But, you know, typically, you know, there's three or four style jobs that we do, and I got different production rates for each one. And so I kind of got a good idea of what they're going to get on a on a rock site, you know, wide open rock site, and I'll speed that production up, you know, maybe 10, 15%.
SPEAKER_00Okay.
SPEAKER_01To kind of lower my price. Lower your price.
SPEAKER_00But okay.
SPEAKER_01Yeah.
SPEAKER_00Yeah.
SPEAKER_02And I would guess, especially on like a larger project, because you know, especially the kind of work y'all do where you're doing dirt work more than anything, uh, you know, underground work, you know, that's gonna be before everything else. So you're kind of at the start of that train, right? Now, each day that's impacted by weather conditions that sets you guys back, could potentially set back the entire project. Yes, but I would just say uh I guess the question that I would ask is, you know, is there just kind of uh whether you call them a gentleman's agreement or just uh standard practice that look, if there's just an excessive amount of rain, like people have some grace there, or do you find that some people are strictly adhere to uh projected timelines?
SPEAKER_01Well, it it all depends on how your contracts are written, which you know, as a subcontractor, the GC, you know, they've got a contract with the owner, they've come to an agreement in their contractual agreement that you know they have a deadline they've got to reach. And so if if our portion, you know, grading excavation side is always one of the first things that happens.
SPEAKER_02Yeah.
SPEAKER_01So if we come in or, you know, if we're if our production slows down because of weather-related issues, uh generally we have a liquidated damage clause in our in our contract. So if we go over our contract allotted timeline, then we have to pay so much per day. But it's you know, we're talking about notes, right? It's really important to note you know, your weather delays when you have them and how long it's too wet to work. And it's not a bad idea to get the GC or the owner's representative that's on site to sign off on your daily report, you know, saying, like, hey, look, you
SPEAKER_02know,
SPEAKER_01we had these rain day today, too wet to work, you know, whatever, get them to sign.
SPEAKER_02Yes.
SPEAKER_01Yes, and then that way, you know, if if you've got their signature somewhere on that page, they've agreed to everything you've written on that page. Uh, so it's not a bad practice to get, you know, to start doing that because it doesn't happen very often, but you can't end up in court or legal, you know, uh uh arguments uh about such things, and you're trying to avoid paying liquidated damages, and then hey, you know, not only do we think it was too wet to work, here's your representative that signed off on our notes saying it was too wet to work in their opinion, also.
SPEAKER_02Which is, I guess, more binding than like, oh, well, we looked at accueather for this date. And it said that it said it didn't rain here. Well, I've had my phone tell me it was sunny outside, and I've looked out and it's been pouring, you know.
SPEAKER_01And it and it's always good, you know, to have somebody from your company to make a site visit. You know, just because it's raining where you're at doesn't mean it's raining on a job site. You know, we've had that happen several times. Go ahead and make that initial job site visit, assess it, and talk to the representative or the owner of the GC like, hey, I'm out here, you know, looks like we've had a half inch of rain or inch of rain, whatever it may be, and it's just too wet for us to perform today. It's not not safe.
SPEAKER_02Right. I mean, that's the biggest concern is safety.
SPEAKER_01And we can't do the quality work that we need to do in these conditions.
SPEAKER_02Because
SPEAKER_01you know, you got trench back filling stuff like that, you know. You don't want to put a pipe in the ground and in a parking lot or road, and you got a year's warranty on that, and then nine months later it settles because you put some wet material in there.
SPEAKER_02Yeah.
SPEAKER_00And
SPEAKER_01now you're up there, you know, taking up asphalt, you know, trying to find out how how deep the bad soil is.
SPEAKER_02Getting yourself in the big bass. Yeah.
SPEAKER_00Yeah. So
SPEAKER_01I mean there's there's a lot of things to take in in you know that can affect your end-of-game deadline. Uh, but you can also get a change in order to extend your time. And those are things you know that you have to request, you know, from the GC or the owner, and like, you know, hey, I'm I'm sending in a request for uh a change uh because of weather delays. You know, we've and you can generally do the math pretty easy. You know, if you've got six months on this job, yeah, they'll generally give you like, you know, so many weather days per month. So say they give you 15 weather days for a six-month job. So I mean you can divide it up pretty quick and see how many days you got each month. So first month you have, you know, you may hit half or more of those weather delays that's in your total contract in the first month. I'm like, hey, you know, we need to go in and ask for more time because this could get out of hand pretty quick.
SPEAKER_02Yeah.
SPEAKER_00So I that so you just answer my question. I guess my question was I guess that the that doesn't influence the GC in terms of projects they're betting on. In terms of the time of year or whatever.
SPEAKER_01No, it doesn't. You know, it's but then that's what you know the request for for time is or request for change is like, you know, we hope that we can achieve this in the allotted time in our contract, but if we have weather delays, even though we're the first ones in, we're gonna slow up when the builders start, you know, the framers or structural guys, when they start doing their work, because now we've pushed them back, you know, three or four weeks, so they're starting three or four weeks late. They may have some delays of their own, and then before you know it's just a kind of chain reaction. Yeah, everybody, you know, and and what happens is like, you know, these contractors have made agreements with other projects that we're gonna start on a certain time.
SPEAKER_02Yeah.
SPEAKER_01So now we've pushed them back three or four weeks later, or month, you know, five, you
unknownknow,
SPEAKER_01five, six weeks later, maybe two months back from starting a project that they've already got on.
SPEAKER_00Okay, well, in that situation, let's just say it got went from bad to worse, then are you, when things clear weather-wise and you're so many weeks behind, are you then looking to bring in a sub to help you knock out something? So you know
SPEAKER_01it's not it doesn't necessarily be a sub, it could be another crew that you might have available.
SPEAKER_00Okay. Yeah,
SPEAKER_01you know, if you've got other crews. I mean, if you're just a one or two man, you know, one or two crew man, then you know you may have to look at a sub. Yeah. But yes, it's not uncommon when you do get behind, and they'll ask you those things, like, hey, when the weather breaks, can you get us extra crew out of here?
SPEAKER_00Yeah.
SPEAKER_01And, you know, so and and if you say yes, you be most cases you better perform. You better get somebody out there. They're not going to let you forget that you made that agreement. Uh so yeah, you know, it's it's it's it's tricky, but you know, once you get the hang of doing stuff like that, uh, you know, it's it's not all that bad. And the main thing is to be up front. Don't let it drag out to the last of the job, you know, or or when you start seeing that you may have a problem and start up, you know, may be in trouble.
SPEAKER_00Yeah.
SPEAKER_01And then like, well, why didn't you say something when we had all the rain delays? You know, why don't you bring this up then?
SPEAKER_00Right. Yeah, leave the whistle thinking you know. Right. Yeah.
SPEAKER_01Yeah.
SPEAKER_00Very hopeful. Yeah.
SPEAKER_01But documentation's key. Make your site visits, get your uh owner's rep, superintendent, whatever he may be, project manager, whatever he may be, that's on that project, get them involved, let them know, like, you know, hey, it's been raining all week. We've made multiple visits out here. Here's my notes for the week. You know, if you agree with these, you know, please sign my daily reports. Uh that way you got documentation to back up, you know, hey, this is legit. You know, they they could not work, it was not suitable in working conditions.
SPEAKER_02CYA clause.
SPEAKER_00CYA clause. Yep, yep. That's
SPEAKER_02right.
SPEAKER_00I like it. Well, man, well, good stuff, Jeff. Thanks for sharing as always. Yeah. Jeff G? Jeff Spencer, it's fun as always. Yeah. Guys, thank you for tuning in to Profit Dig Live. My name is Chris Work. Hey, why you're here? Subscribe to the channel, like the video, leave some comments, let us know what you want to hear or want to talk about. If you're in construction, you obviously need the world's easiest to use job bidding and costing solution. Check us out, profitdig.com.