Learn more about ProfitDig, easy job bidding and costing for construction contractors, at https://profitdig.com
If the show helps you, follow it and leave a rating. That is the best way to help other contractors find it.
The ProfitDig Radio Show
What Is A Change Order? Construction Contract Basics Explained
Use Left/Right to seek, Home/End to jump to start or end. Hold shift to jump forward or backward.
Change orders are a crucial part of construction contracts, but do you know how they work? In this episode of ProfitDig Live, professional construction Project Manager, Jeff Spencer, breaks down what a change order is, when you need one, and how to handle them the right way. Whether you're adding work, removing scope, or dealing with unexpected site conditions, understanding change orders will help you protect your bottom line. Learn the process, avoid common pitfalls, and make sure you get paid for the work you do!
💰 Try ProfitDig for easy construction job costing and bidding: https://www.ProfitDig.com
📢 Like, comment, and subscribe for more construction business tips!
The change order comes about once you have entered a legal and binding agreement, which would be a contract with the owner or G C that you are working for.
SPEAKER_01Welcome to Proper Dig Live. Yes, doing all right. Good,
SPEAKER_00Jay. Are you bud?
SPEAKER_01Doing good. Yeah. What is a change order?
SPEAKER_00The change order comes about once you have entered a legal and binding agreement, which would be a contract with the owner or GC that you are working for. And what a change order is, is you've got a contract that you both have agreed on the scope of work you're doing. When something comes up that's outside that scope of work that you bid on, then that's where a change order comes in. You are requesting by giving information and cost to the GC or owner that you know, hey, our scope has changed, this is what it's going to cost. We are requesting for an increase in our contract amount by this amount by this much.
SPEAKER_01Uh-huh.
SPEAKER_00And it can also be what they call a deducted change order. You have a scope of work that you have bid on, and say they have changed something in design to where if you're bidding utilities, you don't have, you know, maybe some of your footage of pipe went down in your water or sewer, maybe there's a you know a couple less manholes. Uh maybe the grading has changed, you know, instead of moving, you know, 10,000 cubic yards of dirt, now you're moving five thousand yards, you know, cubic yards of dirt. So then at that point, you know, you've got to be able to give a deducted change order because you're not fulfilling the full scope of work you bid on. So you've got to be able to give that money back. So, you know, now you're asking for a decrease in the contract amount.
SPEAKER_01Do I do I just do I take our original bid, just kind of mark through it with the sharpie?
SPEAKER_00No. No, you gotta you gotta go through a proper procedure. You know, you've got to give a breakdown of the unit cost that you're giving back or the unit cost that you're asking to increase, accompanied by a a formal letter which is called a request for change order. Uh and at that point, you know, you kind of write out the change in scope of work, and then say, you know, at the end you say, you know, please see the attached breakdown for the monetary changes that we are uh requiring.
SPEAKER_01So what can bring about the need for a change order?
SPEAKER_00Well, is it any kind of change, you know, versus what you bid on.
SPEAKER_01So I can it can it be that there were some things about the job you were not aware of, you have to do this and that that's
SPEAKER_00no, not really. I mean, most of the time, you know, I mean it could be, you know, like if you don't have a geological report, you know, and that's why it's good to qualify your bids when you build, you know, like for rock, you know, exclude your rock excavation. You know, so maybe there wasn't a GEO report on this project and you encounter rock. Well, at that point, that will be a change order because that's outside the scope of work you bid on. So it's not necessarily always a change. You know, it's dependent on how much information you're giving up front, and then you know, say maybe there's some existing utilities that's there that no one knew about. Uh-huh. And you come across them, well, now these utilities have to be moved. So there wasn't a change to this to the to the drawings. There wasn't a change to your scope of work, it's just something you encountered and no one knew about. So, yes, you know, that would require you know an additive change order as well to relocate those utilities.
SPEAKER_01Have you ever had a circumstance where the clients pushed back on the change order?
SPEAKER_00Yes. Okay. Yeah. And at that point, you know, I mean, most of the time it's like a monetary amount, you know, they don't agree with the money you're charging. And, you know, if you're comfortable with it and that's what you need to do, that change order, then you know, stick to your guns. Because most of the time, you know, they're not going to hire somebody else to come in and do part of your work because then you get into warranty, warranty situations.
SPEAKER_01Okay.
SPEAKER_00Uh so, you know, therefore, they're probably, if it's going to delay their project, they're going to find a way to pay your change order and get you to continue to work in.
SPEAKER_01So you've got a little bit of leverage there just because of the difficulty of switching to a whole a whole other contract.
SPEAKER_00Right. Right. Yeah. Because anyway, you're writing a contract inside a contract for a different sub.
SPEAKER_01Right.
SPEAKER_00And most of the time they're going to try to avoid that. Now, if you just got, you know, a really bad relationship with this GC and it's been, you know, kind of held on both of you from the start, you know, they they may get to a point to where, you
unknownknow,
SPEAKER_00that's one thing you really need to read in your contract, you know, what your exit clause is. You know, it's like, you know, are they going to get rid of me, you know, because you know, they're not happy with me. You know, they've got you know there there's a lot of uh language in a contract, you know, that that that's hidden that you may not understand or see, you know, at a glance, uh-huh, to where they can they can kick you off the job because you're not doing what they call quality work or what they expect to be quality work.
SPEAKER_01Right. Okay, so uh the change order. Does it look like a bid? Does it have bid items and headers? Is it on its own thing?
SPEAKER_00It can, you know, and there again it depends on who your client is, who you're working for. A lot of times some GCs have their own documentation. They want you to format your scope onto that documentation, you know, for that change order. Uh, and then sometimes, you know, I generally like to use my own stuff, and I've got try to stick to that because I feel like I've got myself covered. You know, when you use their stuff, a lot of times it's kind of open-ended, you know. Uh-huh. Uh, so even when I have to use theirs, I will still send my documentation and like, you know, hey, you know, you approve through yours, but I want you to sign mine as well.
SPEAKER_01So I guess it can be handy to use a system like Profit Dig, for example, where you can use those those same items you use to create that original bid to also create your change order. It's all the same format and looks nice and neat.
SPEAKER_00Yes.
SPEAKER_01That's some good information, Jeff.
SPEAKER_00Yes, sir.
SPEAKER_01All right, appreciate you. You
SPEAKER_00bet. Thank you, Jerry.
SPEAKER_01Yes, sir. Y'all check us out at profitdig.com. If you found this useful, man, we would appreciate a like or a share, or if you've got a comment, let us know. We respond to readers' comment or viewers' comments sometimes. Y'all check us out at profitdig.com and we'll see y'all next time.