Practical talk for excavation and sitework contractors and estimators. Bid smarter, run the numbers, and keep more of what you earn.
The ProfitDig Radio Show is a straight conversation about the work and the business behind it. We talk through real jobsite situations, estimating and job costing, cash flow, equipment decisions, and the problems that show up when you are running crews and trying to make a profit.
If you dig, estimate, or run a sitework or excavation company, this show is for you. You will hear from the ProfitDig team and from contractors who do this work every day. No fluff. Just practical talk you can use on the next bid or the next job.
New episodes come out every week.
Learn more about ProfitDig, easy job bidding and costing for construction contractors, at https://profitdig.com
If the show helps you, follow it and leave a rating. That is the best way to help other contractors find it.
The Very Important Differences Between a Construction Bid and Estimate - Make Sure You Get It Right!
•ProfitDig LLC
Use Left/Right to seek, Home/End to jump to start or end. Hold shift to jump forward or backward.
0:00
|
7:19
There are very important differences between a construction bid and an estimate, and it is critical that you use the correct language with customers or potential customers. Jeff Spencer has been bidding work for 30 years so is highly knowledgeable on the subject. Our special guest, contractor Luke Fielder, joined us for this conversation and described his personal experiences related to the matter.
From ProfitDig - the world's easiest to use construction job bidding and costing solution. Save 50% off of your first 3 months (no contract, cancel any time) with coupon code "50off". Visit us today at https://www.profitdig.com.
SPEAKER_00
Explain to our viewers the difference between a constructed dip and a construction. Look, we're changing our formats and all that, I guess. thank you. Thanks. Awesome. Thank you for the hats, Welcome back, man.
SPEAKER_01
Yeah. Thank you.
SPEAKER_00
Thanks. Awesome.
SPEAKER_01
Thank you for the hats, buddy.
SPEAKER_02
I like
SPEAKER_01
you. sashed
SPEAKER_00
away, so I'm going to It's already sashed away, so congrats. Jess Spencer, part of the Chris.
SPEAKER_02
Good
SPEAKER_01
man, how are
SPEAKER_00
you? Good, good. Well, listen, we've had a very in-depth discussion this evening all about bidding and estimating and markup and managing that shit at the line item level. I mean, we've we've been in the weeds, and it's it's pretty cool. I've been doing this discussion. But they kind of raised an interesting question. It seems obvious, but it isn't necessarily obvious based on the language or terminology you may be using. So I want you guys, you're the experts here, explain to our viewers the difference between a construction bid and a construction estimate.
SPEAKER_02
Well, I guess it all stemmed from we were talking about the some guys, well, you know, here's the here we've got your estimate for you. Whenever it's a hard fixed price, which is actually a bid, and you tell a customer, well, I think it's gonna be this, so here's your estimate, and they they have in their head, well, this is what it's gonna cost.
SPEAKER_00
They didn't bring it out for look, this is what it's gonna cost.
SPEAKER_02
That's why I always I I don't hardly ever ever tell anybody a number, you know, sling it from the hip in person, because I'm like, no, I'm I'm not gonna do that. Yeah.
SPEAKER_00
Just
SPEAKER_02
because once you once you tell somebody, especially like an individual who's not in not in this you know, industry on a regular basis, you tell them a number, that's that's the number that they've got in their head already that's gonna cost.
SPEAKER_00
Yeah. Send them a cough.
SPEAKER_02
Yeah. Well,
SPEAKER_01
you know, like one thing, when you're given a hard bid, you know, most of the time you have documents, you know, you've got plans, you know, either a certain percent complete, you know, like you may end up with like 50 or 60 percent drawings, but by the time you get to 70, 80 percent drawings, you know, those are good hard numbers that you can stand behind.
SPEAKER_00
Yeah,
SPEAKER_01
and then you know, if something varies, you know, from those drawings, not from your pricing, but if if the if the drawings change or something changed on site, you have an option, you know, for for change orders.
SPEAKER_00
Yeah,
SPEAKER_01
but like Luke was saying, with the estimate, you know, you're just kind of going out and looking at at this project that someone wants done, there's no documents, there's no plans. You're just looking at a raw piece of ground or whatever it may be, and like, you know, hey, I think you know this is what it's gonna cost.
SPEAKER_02
On average, you know, topsoil is about eight inches, six to eight inches thick around this area, but you know, sometimes it's a relevant field. It could be, yeah, 18 to 2 foot, 18 inches to two foot, you know, that's a big difference because it doesn't just change the amount of topsoil that you're gonna have to end up stockpiling, it also reduces the amount of fill material that you would be able to have to fill with as
SPEAKER_01
well. And a balance site may be an import site, maybe.
SPEAKER_02
Exactly, yeah.
SPEAKER_01
So now you're buying product somewhere else and bringing in to compensate for the extra, you know, 10 to 12 inches of topsoil you had to take out.
SPEAKER_02
Yeah, that's always something we always put in ours. Uh if there's no no kind of geo reports or or you know, test pits, and even with even just digging like test pits, you know, there's still things that can go wrong or that aren't uh consistent with what the geo reports say.
SPEAKER_00
Yeah, but like a small sentence too, you know.
SPEAKER_02
Yeah, exactly. Uh so yeah, it's it's uh it's it's it's it's very hard as far as getting getting numbers together, especially like the less the less information you have, the you know, the bigger the range that it can grow, you know, as far as for your the actual cost. And so, you know, I always try to I always try to put as much details in our our uh scope of work and and uh exclusions and acceptances that you know just because of this, we uh we don't know the less we know, the wider the range could be.
SPEAKER_01
Yeah, exactly. And an easy way to to to explain it is like if you've ever had a fender bender or something, you know, and you take your car to body shop, you get an estimate, and they tell you it's gonna be $2,500. You go back to pick it up and weigh $2,750. You know, there was one more light that was broken, or you know, some screws that were missing, we had to order, you know, then that's the extra cost. But you know, one thing, and I'm sure Luke has seen this too, you know, when you give an estimate and someone wants you to come and do a job, when you hit those situations, you know, when you hit you know the extra 10 or 12 inches of topsoil, don't strip it all. Pull it down and like, you know, hey, we got more topsoil, go get the property owner, come out, you
unknown
know,
SPEAKER_01
or whoever you're working for. So, you know, look, this is the issue. I can either stop and reprice this, or you can get someone else to come in. You know, at this point, you just you know, if you if you want me and pay me what you owe me.
SPEAKER_00
Yeah,
SPEAKER_02
just take it from that point on as at an hourly time and material race.
SPEAKER_01
If you go on and complete the project, you know, do the project, then
SPEAKER_00
ask for more money. Then ask for more money, it's not gonna be good. Yeah,
SPEAKER_01
yeah.
SPEAKER_02
Change orders, change orders can come from both sides, you know. And that's one thing I've also learned, yeah, you don't do anything without writing. I don't care if you can stand right in front of them and be the nicest person you've ever met. You don't do anything.
SPEAKER_01
Right.
SPEAKER_00
That's right, yeah. It's just that they get the job done, and you gotta get paid because you're doing so. All right, well,
SPEAKER_02
yeah, we're we're working on uh we should be getting some our service agreements finally. We uh we ended up having to get a new lawyer, draw up our service contracts. Uh
SPEAKER_00
never ends us, all we're doing. Man,
SPEAKER_02
it's uh there's a lot to it, that's for damn sure. There's a lot to it that you never would have even thought of. Yeah,
SPEAKER_00
yeah.
SPEAKER_02
Absolutely.
SPEAKER_00
That's yeah. Well, we we you know we I mean you've been in business for what?
SPEAKER_02
So we just start we just started the beginning of our third year.
SPEAKER_00
Big third years, yeah. A year longer than I didn't think it's
SPEAKER_02
yeah,
SPEAKER_00
but like you know, it's like yeah, you're working for the business, then you're working in the business. And then you know there's nothing you can do about that until you know
SPEAKER_02
pretty sure my hair's gotten grayer.
SPEAKER_00
I'm sure it's supposed to you
SPEAKER_01
just wait, it gets worse.
SPEAKER_02
Oh yeah, I'm sure.
SPEAKER_00
That's right. All right, well, fellas, Luke, Jeff, I appreciate y'all in. Well, first, like the video, subscribe to the channel, check us out, you know, big awesome tool, probably do that com. See you guys.