Practical talk for excavation and sitework contractors and estimators. Bid smarter, run the numbers, and keep more of what you earn.
The ProfitDig Radio Show is a straight conversation about the work and the business behind it. We talk through real jobsite situations, estimating and job costing, cash flow, equipment decisions, and the problems that show up when you are running crews and trying to make a profit.
If you dig, estimate, or run a sitework or excavation company, this show is for you. You will hear from the ProfitDig team and from contractors who do this work every day. No fluff. Just practical talk you can use on the next bid or the next job.
New episodes come out every week.
Learn more about ProfitDig, easy job bidding and costing for construction contractors, at https://profitdig.com
If the show helps you, follow it and leave a rating. That is the best way to help other contractors find it.
Daily Jobsite Documentation - the CYA Key to Staying Out of Trouble if a Construction Job Goes Bad
•ProfitDig LLC
Use Left/Right to seek, Home/End to jump to start or end. Hold shift to jump forward or backward.
0:00
|
9:50
The ProfitDig guys talk about the importance of daily jobsite documentation. Jeff Spencer talks about using contractors' daily diaries to document information such as jobsite conditions, weather, or any other factors that might affect the work that gets done on a particular day. This information is invaluable in situations such as a court case. You need to be able to explain what happened on a particular day, or set of days.
From ProfitDig - win more jobs and make more money with ProfitDig. Easy job bidding and costing for construction contractors.
It's a great practice for those just starting out.
SPEAKER_01
Right. Um
SPEAKER_02
build good habits.
SPEAKER_00
Build good habits, exactly.
SPEAKER_02
Hello, YouTube. Thanks for tuning in with us this evening. We're so glad you're here. You look great today, by the way. Check us out at profitdig.com. We've got the world's best and most cost-effective costing and bidding solution. Profitdig.com. Check us out. I'm here with Chris Ward and Jeff Spencer.
SPEAKER_01
What's up?
SPEAKER_02
And we were having an interesting conversation earlier about contracts, and another topic came up. So we thought we might uh explore that idea a little bit. The topic we were considering was
SPEAKER_01
diaries. Daily documentation.
SPEAKER_00
Daily documentation. Which is obviously I mean, you you know this more than we do, Jeff Spencer, that that is critical in um on the in an environment where you have multiple employees and foremen and and and superintendents and and whatnot. It's kind of a cover your ass kind of thing. Yeah, it is. Because that way no one can come back and say, well, you know, you weren't able to do this on this day or whatever. But point being is that it's a great practice for those just starting out.
SPEAKER_01
Right. Um
SPEAKER_02
build good habits.
SPEAKER_00
Build good habits, exactly.
SPEAKER_01
You know, and and we what we do, we order those, we order them online. I usually get them in December uh for the following year, but those green, they got green and blue, and I think there's another color out there. We use the green ones. They're called contractors' daily diaries. And they've got all the information in there you need as far as you know what you need to document. You know, you need to document the weather each day, the temperature, if it rained, if it didn't rain, even if it's cloudy. Right now, if it's cloudy, you never know what may come out in a court case, you know, what information may be crucial to that particular case and what may have affected, you know, the job that day. You know, just like concrete, for instance, you know, it it doesn't cure as fast, you know, when it's cooler out. You know, it's yeah, you know, and it gets to a point where it could freeze, you know, when you pour concrete. Uh so you know, that's just one instance. Grade work. If it rains that day, you know, if they say, well, you only worked 10 days this you know that month, well, you know, we had you know 11 days worth of rain.
SPEAKER_02
Yeah. And you got that documented.
SPEAKER_01
Right, you got it documented, yeah.
SPEAKER_00
So
SPEAKER_02
who's who's keeping these diaries? Is this everybody on the
SPEAKER_01
process?
SPEAKER_02
Your foreman's foreman on
SPEAKER_01
the on a project needs to keep them. And you know, if you're on one job, it's pretty easy to do, but you know, GCs usually have a uh superintendent on site, you know, throughout the day. Go a step further. Go to that GC superintendent, it's like, you know, hey, here's what we did today. Will you do you mind signing the bottom of my page here?
SPEAKER_00
Yeah.
SPEAKER_01
Then that way, you know, you've got the GC that you're in a contract with agreeing that you know this is what happened that day. Yeah,
SPEAKER_00
and
SPEAKER_01
so that signature goes a long way if it comes down to going to a court case.
SPEAKER_00
Yeah. Have you ever had a GC go out or superintendent be
unknown
like,
SPEAKER_00
I don't know, man. Like, I saw what you did, I don't necessarily want to sign.
SPEAKER_01
Yeah, yeah, there are. And
SPEAKER_00
well, you
SPEAKER_01
know, and and and you can go back to your project manager and say, hey, you know, so and so didn't want to sign my daily diary. And you know, me as a project manager, I may reach out to the project manager for the GC that I'm working with. Yeah. Like, hey man, you know, if you don't mind, can you just get your superintendent to kind of read through our notes every day? If he agrees with it, you know, sign it. And, you know, I pretty much, you know, it's like, yeah, you know, if that's that's the work y'all did, then yeah, we'll sign it.
SPEAKER_00
Acknowledge that. Absolutely.
SPEAKER_02
We're not trying to pull a fast one on anybody. We're just trying to make sure that we build good habits and that we can represent the work that we did that day and we've got a record of it.
SPEAKER_01
Right.
SPEAKER_00
Yeah, yeah. But
SPEAKER_01
yeah, good notes, you know. I mean, sure, you can use like a spiral notebook or anything else, but you know, it looks better to have where you're not sitting there flipping back and forth through your notes trying to find things if you know the date, because you've got you start on January 1 with your new book. And you know, you go each day has got its own page.
SPEAKER_00
Right.
SPEAKER_01
So every day is documented. So it's a lot easier just to flip through there and find a month and a day you're looking for, and like, you know, hey, this is what we did.
SPEAKER_02
Yeah.
SPEAKER_01
So I mean, yeah, you can keep notes on anything, but you know, that's why those books are out there. I think they're like 50 bucks. And you know, if you got four or five forms, you know, two or three hundred bucks a year is is really cheap for the CYE factory
SPEAKER_00
cheap insurance. Yeah, yeah, absolutely. Yeah, yeah. Yeah, I guess you
SPEAKER_02
could even just have one per project, right? Depending on the size of the crew.
SPEAKER_01
You can, but you know, we typically just give each crew one in January, and then it starts, he turns them in to us at the end of the year when he gets his new one, and you know, we generally label on our, you know, the the the foreman's name on our book so we know if we're looking for a certain one, we know who's whose it is. Yeah,
SPEAKER_00
yeah, yeah. Reference it.
SPEAKER_01
But we keep them up to three years and then we dispose of them.
SPEAKER_02
So there's site conditions for the day, like environmental conditions, there's work and maybe materials received. Right.
SPEAKER_01
And it could be, you know, like if you're on a site with other contractors, it could be, you know, like I was not able to perform my work today because contractor so-and-so was in my way.
SPEAKER_00
Yeah. Yeah.
SPEAKER_01
And we got with the superintendent, and you know, he tried to get them to get out of the way, you know, he wasn't successful. You know, those kind of things need to be
SPEAKER_00
documented. Yeah, slowly. Yeah.
SPEAKER_02
Well, especially once it starts getting towards the end of the job or even after the job is completed and something goes wrong, having that documentation could really go a long way. Even
SPEAKER_01
though if you're on the job,
SPEAKER_00
you too. Right. I mean it's an interruption. Yeah, the thing about betting, if I'm going back and I'm like, you know what, every time we find ourselves in this type of you know, uh layout or situation or this stage of the project, whatever it might be, it's like, yeah, well, if there's a common theme there, it's documented for me. Now I may decide that I need to charge more for you know a particular type of job site. You know what I mean? That's you know, it could be
SPEAKER_01
pictures. You know, take your pictures. You know, I've I'm sure I hope I'm sure that most project managers and owners have a uh electronic file on each job. So my foremans and stuff will send pictures in on each job, maybe not daily, but at least weekly, and then I store them in a folder for that job. And and the reason being is like there's other contractors working on a job, not just you. So maybe you've got a pipe you put in the ground, and then here comes another contractor he's digging. Well, maybe you see or have noticed that he's broke some of your stuff and did not repair it correctly, or come and get you or whatever, you know, have you to repair it correctly? You know, document that, get pictures if you can, and then later on down the road, if you have trouble with the materials you put in, and it happens to be that same spot that he dug through it or damaged your material or light, then you know, hey, this is who done it. It wasn't us.
SPEAKER_00
Yeah,
SPEAKER_02
yeah.
SPEAKER_00
That's good to know, man. That's that's all good stuff. And like you said, Jeff, yeah. Build good habits.
SPEAKER_01
And that's another thing too, you know, it's like, yeah, sure, you know, I want every man to pull his own weight on a crew, but a working foreman is not always the best uh utilization. You want a foreman that can, yeah, he can work and keep his crew going, but he also needs to be looking and planning a hand for the next day. He needs to be looking at stuff that's going on around him on site, and anything that's gonna that could possibly prolong your your scope of work, then he needs to be on top of that and see it. If he's sitting on an excavator or if he's sitting on a loader, he's not gonna see all that stuff because he's gonna be focused on what's going on there. You know, so I mean, yeah, he needs to be there to run the crew and make sure they got work to do, but he also needs to be able to document and look over the project, plan ahead, and also look back and make sure that everything that he's done is protected.
SPEAKER_00
Yeah.
SPEAKER_02
Yeah, it's interesting that you bring that up. I've been dealing with that in my job quite a bit recently with scope creep, different stakeholders, different, different job positions. And yeah, I mean, if you've got a foreman that's out there running a shovel, yeah. That's a low value utilization of that foreman's time. It's probably also not satisfying
SPEAKER_01
for him.
SPEAKER_02
Probably not. He's looking he's looking to elevate his career.
SPEAKER_00
Yeah. Oh, yeah. Well, I mean honestly, I mean, a foreman, I could be wrong, but I can see an essence where the weather's beautiful. Well, yeah, let's get up there for a while. We'll get in there. Yeah, and he wants he wants to get on that equipment. Yeah, moving dirt. He wants to move some stuff around, you know. He had done that before. It's fun. Well,
SPEAKER_01
that's one thing, you know. I couldn't even vouch for that. I've been in project management for several years now, and one of the main things I miss is sitting on that piece of equipment and running it.
SPEAKER_00
Yeah.
SPEAKER_01
I do. Yeah. You know, that was one of the things I really enjoyed about construction was going to, you know, moving dirt, doing things, you know, being able to see what it was supposed to look like and then make it happen. Mm-hmm.