Practical talk for excavation and sitework contractors and estimators. Bid smarter, run the numbers, and keep more of what you earn.
The ProfitDig Radio Show is a straight conversation about the work and the business behind it. We talk through real jobsite situations, estimating and job costing, cash flow, equipment decisions, and the problems that show up when you are running crews and trying to make a profit.
If you dig, estimate, or run a sitework or excavation company, this show is for you. You will hear from the ProfitDig team and from contractors who do this work every day. No fluff. Just practical talk you can use on the next bid or the next job.
New episodes come out every week.
Learn more about ProfitDig, easy job bidding and costing for construction contractors, at https://profitdig.com
If the show helps you, follow it and leave a rating. That is the best way to help other contractors find it.
When to Use Different Types of Pipe in Underground Utility Construction
•ProfitDig LLC
Use Left/Right to seek, Home/End to jump to start or end. Hold shift to jump forward or backward.
0:00
|
7:39
ProfitDig After Dark... not really! But it is Chris and Jeff talking about pipes! As Jeff explains, come municipalities require certain brands or types of pipes for specific applications. If you are engaged in underground utility work, it is critical you understand the different types of pipe and when to use what. Jeff is an expert in underground, so he knows what he is talking about.
Another helpful video from your friends at ProfitDig! Check us out at https://www.ProfitDig.com. Easy job bidding and costing for #construction contractors.
SPEAKER_00
Oh, but Jeff, uh just thinking like um think about the different types of pipe required to complete a task for I mean it's
SPEAKER_01
not
SPEAKER_00
thank you. My goodness, we gotta put the word out. What is going on, everybody? My name is Chris Work. I'm here with my partner Jeff Spencer. How's
SPEAKER_01
it going, Chris?
SPEAKER_00
Going good, man. How you doing?
SPEAKER_01
Doing well.
SPEAKER_00
Awesome. Listen, uh, if your kids are up, you may want to go ahead and put them to bed because this is the Prophet Dig construction show. And I'm just kidding, I was like expecting like some big boom again, but nothing really happened. Um no, it was uh it was kind of an awkward thing. Um I um I didn't, but someone earlier was was was talking to Jeff about pipe. And they started by saying, Jeff, you're an expert at laying the pipe. It was just the way they said it um uh inadvertently, obviously. Um was Jeff, you you know, I mean you you're a family man, so you you also know how to lay pipes. So um
SPEAKER_01
pretty much made my career laying up
SPEAKER_00
right 24-7. Yep. 24-7. Um no uh gosh, maybe you really should put your kids to bed for this episode. Uh we need to we need to clean this up real quick. Um no, but Jeff, uh just thinking like um thinking about the different types of pipe required to complete a task for a municipal municipal
SPEAKER_01
municipality.
SPEAKER_00
Thank you. My goodness, I could not spit the word out. Um and just how like from you know one city to the next that can change and and this and that. So
SPEAKER_01
well, not necessarily from one city to the next, it's like districts. You know, you hit you may have multiple utility districts in in one city. Oh one county.
SPEAKER_00
Yeah, yeah, absolutely. Okay, okay. Just
SPEAKER_01
from district to district, you know, depending on what their their specifications may be.
SPEAKER_00
Yeah, well, in your experience, is it fairly common to experience uh a difference between some of the requirements and
SPEAKER_01
it's a lot of different
SPEAKER_00
things? It is,
SPEAKER_01
and you know, a lot of them, you know, will somewhat, you know, require certain brands, you know, of materials they want you to use. Uh like a lot of municipalities, like Metro Nashville, you know, pretty much everything you do in Metro is either gonna be duckled iron pipe, uh, or it's gonna be, you know, copper for your water side. And on sanitary sewer, it's gonna be sometimes, you know, duckled iron is required on sanitary, depending on the depth or the shallowness of the pipe. Uh also, you know, you got SDR 26, SDR 35 sewer pipe, PVC, you know, is is gonna be required. Uh and there's a lot of you know different types of PVC pipe you can use as well for water.
SPEAKER_00
Okay, okay. And you mentioned uh like specific brands that that they uh recommend. Doesn't matter, you know, doesn't mean necessarily have to absolutely purchase those brands, but uh
SPEAKER_01
I mean you may have one municipality, you know, it's a stickler, like you know, this is the only brand we're gonna accept. Uh but for the most part, you know, like when you get a bid package and you're gonna bid this municipal project, you know, they're gonna just I'm gonna throw out a couple names there. It may say like American or Griffin pipe, if it's ducked a lion, and they but they'll they'll call it out, you know, like say may say American pipe or equal to.
SPEAKER_00
Or equal to.
SPEAKER_01
Yeah. As long as it's the and what they're saying is like, you know, hey, we prefer American, but if Griffin has the same classifications on our pipe as what what we're requiring through American, then you're welcome to use Griffin pipe.
SPEAKER_00
Okay, okay. And and I assume that is noted on your bid.
SPEAKER_01
Uh well, I mean
SPEAKER_00
submit or not. Whenever
SPEAKER_01
you're whenever you're bidding a project, when you are awarded the job, you're becoming a low bidder, at that time you put together a submittal package. You know, this is all the materials that you're going to use, and so you hand that over to the the municipality.
SPEAKER_00
Right. And that and that's where I'm identifying the brands.
SPEAKER_01
The brands and the classifications for the brands I'm using. And they may come back, you know, and and 95% of yours may be accepted, and they may circle a valve or something, say, you know, well, we really want like a Mueller valve, or you know, we want uh an American valve, whatever it may be, or uh one of M and H, whatever it may be, or or fire hydrant.
SPEAKER_00
Okay. So,
SPEAKER_01
you know, at that point, then you know
SPEAKER_00
I gotta get back on, I gotta get on the phone and get new quotes depending on the size of the project. Not
SPEAKER_01
necessarily new quotes, but I mean, at this point, I have decided on a supplier that I'm using Based off of his pricing that helped me get the jobs.
SPEAKER_00
Well, sure, sure.
SPEAKER_01
And so I'm gonna call that supplier up and like, you know, hey, you know, you quoted uh American vows and American fire hiders, but they want muter.
unknown
Uh
SPEAKER_01
what are we gonna do? You know, I mean, how are you gonna be able to help me? Can you get them for the same price? Are they gonna be more price? You know, I'm locked in. I've already given a bid, so I gotta do it. So at that point, you know, you may have to eat a little bit of money uh because you're locked in at those prices. You know, you can't you can't go back and ask for a change order.
SPEAKER_00
Gotcha. Yep. All right, all right, that makes sense. So it really doesn't sound like that as a contractor, you don't necessarily have a lot of leverage in that position. I mean,
SPEAKER_01
no,
SPEAKER_00
you're just going with the quality product. Here's my cost, this is what I'm gonna charge. And if it comes back that they're dissatisfied with the valve manufacturer that you've chosen, or they are just sold on this other, you know, brand because that's what they use in all the other jobs or whatever, then they're just gonna have to act on it.
SPEAKER_01
And just like you know, like municipal work and and like say T Dot work, you know, something of that stature, you give most of the time you give unit prices. So you've got X number of valves at such and such price, X uh uh linear feet of pipe at such and such price. So your change orders, whether it be negative or additive, at that point they use your unit price. So say you got a thousand feet of six-inch pipe. Well, we're gonna take two hundred feet off. So whatever unit price you give, that's what you get back.
SPEAKER_00
Okay.
SPEAKER_01
So I mean it's pretty cut and dry. Yeah. And if they say they want to add a thousand feet to that thousand. So now whatever unit price you give, it just doubles up.
SPEAKER_00
Okay. All right. Well, Jeff, good stuff as always, man. And uh you do know your pipe. So um check us out at profitdick.com if you need a job bidding and costing solution while laying your pipe. Um, I guess I'll uh leave it at that, Jeff. I don't know where to go. I hope the kids have been put to bed because this has been the uh uh the adult version of the Profit Dick Construction show. Check us out, profitick.com, subscribe to the channel, like the videos, leave some comments, let us know what you want to talk about, and we'll see you soon.