Practical talk for excavation and sitework contractors and estimators. Bid smarter, run the numbers, and keep more of what you earn.
The ProfitDig Radio Show is a straight conversation about the work and the business behind it. We talk through real jobsite situations, estimating and job costing, cash flow, equipment decisions, and the problems that show up when you are running crews and trying to make a profit.
If you dig, estimate, or run a sitework or excavation company, this show is for you. You will hear from the ProfitDig team and from contractors who do this work every day. No fluff. Just practical talk you can use on the next bid or the next job.
New episodes come out every week.
Learn more about ProfitDig, easy job bidding and costing for construction contractors, at https://profitdig.com
If the show helps you, follow it and leave a rating. That is the best way to help other contractors find it.
Tips for Bidding Underground Utilities from a Seasoned Construction Project Manager
•ProfitDig LLC
Use Left/Right to seek, Home/End to jump to start or end. Hold shift to jump forward or backward.
0:00
|
9:24
The ProfitDig guys talk about bidding underground utility jobs - something Jeff Spencer knows a LOT about! When looking at a specific project, the specifications limit what you can and can't do on a project. Ease of accessibilty is a huge concern. How hard is it going to be do to get your equipment moved around? Where will you have to store your materials? Different types of materials will also greatly affect your bids. Make sure you understand job qualifications. Is stone backfill required? Do your suppliers have the necessary approved supplies you will need?
These are just a few of the items we discuss that have a tremendous impact on how profitable an underground utility job will be for you.
From ProfitDig - bid jobs easier and make more money.
https://www.profitdig.com
SPEAKER_00
Good point, so I'm new, I'm getting started. Let's say I'm an underground utility contractor. Um Jeff, what am I thinking about during this bid process when I'm putting these numbers together? Yeah, we got some tips, yeah. Like I'm just getting started. Fantastic. What is up, party people? Welcome to the Prophet Dig construction show. My name is Chris Work. I'm here with our resident expert, Jeff Spencer.
SPEAKER_01
Don't know about the expert, but you're gonna end.
SPEAKER_00
Well, I don't know. I'd say you're doing pretty good. I
SPEAKER_02
appreciate the title of resident amateur.
SPEAKER_00
Okay, resident amateur Jeff Givens. Um, also our uh chief IT and development architect for Profit Dig, which is probably the best construction and job costing application on the planet. It's so easy to use. It's only $99 a month. It'll help you enhance your bid process. It allows you to track your cost at the line item level on every bid you create. Check it out, profitig.com. Well, guys, we're always creating content. You know, it sometimes it starts to feel like you're you're talking about the same things over and over again, and then you look back and you're like, you know what, hell, we haven't really talked about this. So, you know, we obviously target, I mean we target everyone in construction, but I feel like even more specifically, sometimes I feel like I'm going after the guy who is just getting started because they don't, you know, cash flow could be an issue. Great, we have a killer product that that's very inexpensive for you.
SPEAKER_02
I don't like YouTube videos when I'm trying to get into something too. So
SPEAKER_00
absolutely, absolutely. So that's the whole point. So I'm new, I'm getting started. Let's say I'm an underground utility contractor. Um Jeff, what am I thinking about during this bid process when I'm putting these numbers together? Yeah,
SPEAKER_02
we got some tips. We
SPEAKER_00
got some tips, yeah. Like I'm just getting started.
SPEAKER_01
Well, you know, first and foremost, when you're looking at a specific project, what area is it in? Different municipalities have different specs. Okay. Uh, you know, and your specifications limit to what you can and can't do on a project. So it could slow your production down, you know, it could be a lot of things that alter you know what you do. So that's the first thing. Be familiar with the specs in a county or the district you're working in to make sure you get along with the inspector. That's one of the worst things you want to do right off the bat is get an inspector that's not gonna be happy with you, and he can make it tough on you.
SPEAKER_00
Take inspector fishing. Got it. Okay.
SPEAKER_01
And then, you know, next would be, you know, uh ease of accessibility. You know, how easy is it gonna be to get your crews in this job, get them out, get materials in and out. Uh, are you gonna be working around other contractors, other scope, you know, you're doing other scopes of work? You know, is it gonna be a congested site, a wide open site? You know, what's that gonna look like? So that's gonna be play a big role in your production, it's gonna be a big role in like whether you have to store your materials off-site and bring them on a little at a time. Uh, you know, so look at accessibility. All right. Uh, another thing, you know, is look at always be aware, like you go back to your specs, you know, what type of materials are you using? Because, you know, like if you're a utility contractor and you bid a job because you think you can use PVC, but then it turns out that you got to use ductile iron, well, you know, you're looking at, you know, depending on the size of pipe, but it could be 20 to 50 percent more expensive for ductile than what it is for PVC.
SPEAKER_00
Okay.
SPEAKER_01
Uh so you know that that's the key things that you really got to look at.
SPEAKER_00
Okay.
SPEAKER_01
Uh look at your your uh job qualifications as far as the GC you may be bidding to, or the engineer, what they call out, you know, a lot of times if you're in the in a
unknown
uh
SPEAKER_01
proposed paved area, like a parking lot or a street, uh, you know, like generally when I bid, you know, I I bid mine to use uh uh compacted spoil material for backfill.
SPEAKER_00
Okay. So
SPEAKER_01
what that means is like when you dig out your spoils, you lay them on the bank and then you put them in lifts and compact them. Well, if you're in paved areas, they may require you to use a hundred percent stone backfill.
SPEAKER_00
Well,
SPEAKER_01
stone right now is running over $28 a ton.
SPEAKER_00
Okay.
SPEAKER_01
Yeah, so you know it's it's very expensive, and you you may be, you know, depending on the size of your job, you know, you may have anywhere from a thousand to ten thousand tons of stone, you know, depending on what it may be.
SPEAKER_00
Okay.
SPEAKER_01
And so, I mean that can get pretty costly pretty
SPEAKER_00
quick. Yeah.
SPEAKER_01
And uh, but you know, no, know what you you can do on your backfield, what you can use. Uh make sure that uh you're coordinating with your supplier to make sure you get the right materials on site that the city, you know, have approved. Uh, you know, I've been in some situations before we send in some middles, the middles get approved, and then all of a sudden we get a different brand of product on site. And, you know, and that's happened just here in the last year, year and a half, when materials got so scarce you couldn't, you know, was having trouble getting pipe, meters, and stuff of this sort. So our suppliers were trying to keep us in materials, but they were changing the brands, they was getting different brands.
SPEAKER_00
Okay. And is that a concern? Because you have to, as the contractor, I guess, have to warrant you that material, right? Yes, we have to. Is there a concern there for you as the contractor? Not so much. I mean,
SPEAKER_01
because you know, one's just about as good as the other, the way I look at it. But the main concern is like I've sent in a cemental package, it's been approved by the utility district, and then if if they have a most utility districts have brands that they like to use, you know, whether it be Ford or Mueller, American pipe, Griffin pipe, whatever it may be, you know, that's the type that they want in their system. And so if you bring in something different other than what they have approved, then if they don't catch it, you may have several feet in the ground, and before they do catch it, well, now you're taking it all back up.
SPEAKER_00
Oh, approval on the actual bracket. Okay.
SPEAKER_01
So, you know, once you know, make make sure that you're coordinating with your material supplier and getting the right materials on site that have been submitted and approved by your engineer and uh by the the municipality.
SPEAKER_00
Okay. You know, I never knew that, which sounds silly, but so if I'm when I'm putting my purchase in for materials, am I specifying the brand or am I just buying the brand I know they're going to have?
SPEAKER_01
No, whenever I when I bet a job, I get a quote from my material supplier, he quotes certain products because he's supposed to be familiar with the districts that you're working for. So
SPEAKER_00
it's like,
SPEAKER_01
you know, they'll allow this, they'll allow that. So that's what he sends me in my cemental package. I send it in, they review it, and then they'll either approve it or they'll approve as noted. They'll send it back, you know, or they'll won't approve it at all. They'll s and as noted is like, you know, they approved all the products. Well, here's one or two products that are like, you know, we want this changed on this, want this changed on that. So at that point, you send it back to your supplier. So submittals are approved, but here's a couple items that you gotta you gotta do this on. In either a different name brand or a different style or something. Okay. And then they've got a you know, it may be a price issue there, you know, I may have to eat a little bit or something if it costs more money. But uh, but there's a lot that goes into it, you know, as far as getting your submittals approved and getting your materials on site.
SPEAKER_00
Well, that's awesome. Appreciate the insight, Jeff Spencer. Sir, yeah, and that's it's funny, you know. I've I've learned so much about construction uh just since we formed Profit Dig, you know, a few years ago, and we've never discussed that.
SPEAKER_01
The actual
SPEAKER_00
manufacturer of material. So I just found that interesting. So I hope that is helpful for you, Jeff Gibbons. Pleasure as always, producer Jerry. Appreciate all the work you do. Check us out at ProfitDig.com. Enhance your bidding process, track your job costs at the line item level on every bid you create, find out exactly where you are making or losing money. Subscribe to our channel, like our content, leave us some comments, let us know what you want to talk about, and we'll see you soon.
SPEAKER_02
You know, I and I heard that people who subscribe to the channel, they're 20% more handsome.
SPEAKER_00
And it increases your odds of winning the lottery. It's it's odd. I don't know. But yeah, don't be left behind. We'll see you soon.