Practical talk for excavation and sitework contractors and estimators. Bid smarter, run the numbers, and keep more of what you earn.
The ProfitDig Radio Show is a straight conversation about the work and the business behind it. We talk through real jobsite situations, estimating and job costing, cash flow, equipment decisions, and the problems that show up when you are running crews and trying to make a profit.
If you dig, estimate, or run a sitework or excavation company, this show is for you. You will hear from the ProfitDig team and from contractors who do this work every day. No fluff. Just practical talk you can use on the next bid or the next job.
New episodes come out every week.
Learn more about ProfitDig, easy job bidding and costing for construction contractors, at https://profitdig.com
If the show helps you, follow it and leave a rating. That is the best way to help other contractors find it.
Cut and Fill: A Construction Man Explains What It Is and How You Can Use It to Increase Profits
•ProfitDig LLC
Use Left/Right to seek, Home/End to jump to start or end. Hold shift to jump forward or backward.
0:00
|
5:33
The ProfitDig guys talk about "cut and fill," a concept that anyone engaged in construction needs to understand. It is a simple concept, but one that is essential for preparing a level construction site. It can also allow you to increase profits if you are strategic about it.
From ProfitDig - easy job bidding for construction contractors. Starting at $99/mo., no contract.
Um, I have something serious to talk about just into what the hell is going to feel and what does it mean? Hey guys, Chris Work here from Profit Dig. I'm here with my resident expert, Jeff Spencer, Jeff Givens. We got producer Jerry behind the lens here. Check us out, Profit Dig.com. Have the greatest bidding and job costing tool a young construction owner can have. It's very inexpensive. But that's not why I'm here. Um I have something serious to talk about. Jeff Spencer. What the hell is cut and feel? And what does it mean?
SPEAKER_01
Well, in grade work, you have a site you're working on, whether it be dirt, rock, mix, it doesn't matter. You have cut areas, which is where you're taking raw ground. So you know it's kind of easy to picture, you know, like if you're if you're if you're looking out across a field, you see a hump in the field. Well, now this hump has become a developed area, or want to become a developed area. So engineers generally try to design a site to where it will what we call balance or as close to balance as possible, depending on what the owner is wanting to do with the site. So you take as much raw material that's available, so you got some low areas over here. So you're gonna take this knoll or this hill we're talking about at your cut area. We're gonna cut that down. We're gonna transport it over here and put it in the lower area to bring it up to grade, which is called a failed area.
SPEAKER_00
Okay.
SPEAKER_01
And if your site is close, we generally call it like cut to shift. So we cut it over here and we shift it to this area and fill it.
SPEAKER_00
Okay.
SPEAKER_01
And so as this goes down, this comes up. And in key, in theoretic key, you know, you're thinking about balancing the site. So if you've got a level site, is there enough material here to bring this up to make it level? If not, then we gotta have import material.
SPEAKER_00
Bring it in.
SPEAKER_01
So you got to cut the fill, try to balance the site. There's not enough. So now we've got to bring material in from the quarry, a borrow site. There may be somewhere on site there that you can have a borrow pit, you know, somewhere else that you can excavate and get borrow material to finish up your fill. But you've balanced out, well, now this hill is not, you got all your fill done. Now this hill is still, some of it's still here. Well, it's got to go on down. This is what we call cut to export. So we no longer need this material on site. We've balanced everything out. We've got to get rid of the excess. Okay. So now we're gonna haul this off-site. And where
SPEAKER_02
do you haul it?
SPEAKER_01
Well, that's what I was about to tell you. If you are lucky enough on your bids or a big enough contractor, so you've got several sites there within a five, six mile radius. So maybe you need some fill material. We're talking about borrowed material. What a go, you've got to bring in. Well, maybe you've got material that you can sell off of this site, this other site that you've got, and theoretically, I mean, you've got this other site figured to use, you know, bought bar material, so you can buy it at a reduced rate over here, help this job be more profitable because you're going to have to haul it off at your expense, and then now you're selling it over here to another site at a cheaper rate. So you estimated X amount of per yard to haul it off over here.
SPEAKER_00
Nice.
SPEAKER_01
So, you know, just say it's $35 a yard, what your haul-off is on this over here. So you're selling it over here for $10 a yard, so you've made a lot more money over here.
SPEAKER_00
Yeah, marketing big time. And you had
SPEAKER_01
$40, $50 a yard to haul it in over here, and you haul it in for $10. So I mean, fantastic. So, but if not, you've got to haul it to a designated dump area or somewhere else, you know, you've got to get rid of it, and you may have to pay to dump it. So that's worst-case scenario. So you've got to figure that in your bid, you know, that's why your haul-off cost is so much. But that's the difference. I mean, cut to fill is cutting down one area, filling another area on site to try to help it balance. Cut to export is getting rid of excess material you don't need on site. And in uh borrow material is material that you gotta have from another site, another quarry, or somewhere that you gotta get brought in to finish filling your site at the grade.
SPEAKER_00
Well, fantastic. Jess Petra, I appreciate your insight as always. Yes,
SPEAKER_01
sir.
SPEAKER_00
Jeff Givens? Always a pleasure. Producer
SPEAKER_02
student.
SPEAKER_00
Exactly. Same likewise. And I tell you what, as a contractor, if you're using Profit Dig and you are tracking your job costs on that line item, you'll know exactly how profitable or not. Not so profitable you are.
SPEAKER_02
Yeah.
SPEAKER_00