Practical talk for excavation and sitework contractors and estimators. Bid smarter, run the numbers, and keep more of what you earn.
The ProfitDig Radio Show is a straight conversation about the work and the business behind it. We talk through real jobsite situations, estimating and job costing, cash flow, equipment decisions, and the problems that show up when you are running crews and trying to make a profit.
If you dig, estimate, or run a sitework or excavation company, this show is for you. You will hear from the ProfitDig team and from contractors who do this work every day. No fluff. Just practical talk you can use on the next bid or the next job.
New episodes come out every week.
Learn more about ProfitDig, easy job bidding and costing for construction contractors, at https://profitdig.com
If the show helps you, follow it and leave a rating. That is the best way to help other contractors find it.
Consequences of Change Orders on GMP Construction Jobs
•ProfitDig LLC
Use Left/Right to seek, Home/End to jump to start or end. Hold shift to jump forward or backward.
0:00
|
12:56
The ProfitDig guys answer a question a viewer had asked in a video comment. When you bid a GMP ("guaranteed maximum price") contract, you are guaranteeing a maximum price for the customer. However, sometimes change orders are required that will affect your scope of work. You must be careful to qualify your bids to make sure you are protected in such a case. When the GC is locked into a particular price, you are as well. But sometimes mistakes happen that require change orders. Who is to blame when mistakes are made? Can you charge more when extra work is required because of change orders?
General Contractors like GMP contracts because they are good money, but make sure you don't get burned from the mistakes of others!
From ProfitDig - easy job bidding and costing for contractors. No contract. Low monthly cost. Money back guarantee.
We had a uh a comment uh it's been about a month, um, but it's a really interesting question, Jeff. I thought we'd we'd talk about it for a minute if you want to. All right, so here is a question that was submitted to uh our channel.
SPEAKER_01
Hello guys. Chris Work here from Profit Dig. Hope everyone is doing well. Got Jerry Work here, Jeff Spencer, my comrades from ProphetDig.com. It's good to see all of you.
SPEAKER_00
All right. Yep.
SPEAKER_02
Said hello back, yeah.
SPEAKER_01
Put your device away. That's unprofessional. Casey slight, man. Casey slight, yeah. Well,
SPEAKER_02
they could have been all around it. It could have been a Prophet D customer and didn't need a little help, so.
SPEAKER_00
It could have been. It could have been, well, you know, no, I didn't need to.
SPEAKER_01
We'll get with you shortly.
SPEAKER_02
Yeah. Yeah.
SPEAKER_00
All right. Well, Jeff, you know, sometimes we get behind on responding to comments on our YouTube videos, which we love. We do. Man, we love it when you guys, especially when you ask us questions.
SPEAKER_02
Yes. Um, any kind of feedback, yeah.
SPEAKER_00
Something you want to know, ask, and we will do our best to give you an honest answer. So we had a uh a comment, uh, it's been about a month, um, but it's a really interesting question, Jeff. I thought we'd we'd talk about it for a minute if you want to. All right, so here is a question that was submitted through uh our channel. It says, I don't understand why the architects and engineers never suffer the consequences of change orders. What will happen if there was an error during permitting and during construction, the contractor needs to change the scope sum in time? In other words, the city and the architect did not notice a mistake in the drawing and then it was built. How does that affect the GMP?
SPEAKER_02
And that's a very, very good question. I mean, it's well, you know, from past videos of stuff we've done, you know, I've told y'all in the past, since they start doing GMPs, which a lot of y'all that may not be familiar, ever bid on a GMP job. GMP stands for guaranteed maximum price. So when you bid a GMP project, your GC that you may be bidden with has put together a group of subs he's getting prices from. So you get the con you get the the the 80-90% drawings that you bid on, and these are are contract drawings, you know. When they get 80% plus, you know, you can go to contract with these drawings. Anyway, so you've got these drawings, and what she's what what the customer's talking about, you know, or the the comment is uh, you know, who is liable in a GMP? Because you've already given the guaranteed maximum price. If something changes or something's not right, why if most of the time it's a it's an error or a mistake that was made by the architects or engineers? So that's a very valid question, very good question.
unknown
Uh
SPEAKER_02
that's one reason it's very important to qualify your bid. Give as much detail about the scope of work you're bidding on. Always give the the last date of the revised drawings that you may bid on, give the date of them, the page numbers you bid off of. Try to give as much detail on everything you do to prepare this bid to the best of your ability. The more information you have, the more you protect yourself. Uh so when this GC is locked in in a GMP, you're locked in as well to the price you gave them. So they're expecting you to do your whole scope of work uh without asking for a change order, asking for more money. And in a theoretic type scenario, you know, that should work, but it doesn't always work. Uh just like this person here said, you know, there's always changes that happen, or the architects or engineers miss stuff. One reason is because they weren't prepared. You know, they're being pushed to get these drawings out by a certain date. Oh,
SPEAKER_01
is that yeah, they're under a deadline too.
SPEAKER_02
Yeah, they're under a deadline too. You know, they're they're doing the best they can, but they're again, they should suffer some responsibilities, but it's never that way. They get paid a lump sum amount to prepare these drawings, and then for the duration of the job, they get a percentage draw the whole time that job's going on. So, you know, they really are not out of pocket any liability. So it's it's it's kind of kind of sucks in a way, to tell you truth. Because it's all passed on to the owner. And that's that brings me to the next part. The owner does this, which they are they they may not know it, but in a GMP, they're going to pay a higher rate of construction. Because your GC, every sub that has been to that GC that's ever dealt with a GMP, they've locked in a percentage amount for the hiccups, you know, what was missed, the unforeseen.
SPEAKER_01
Because they assume it's coming in.
SPEAKER_02
Yeah, because you know they're they know that their change orders are going to be few and far between, if any. So when they're doing a GMP job, they are elevating the cost by an X amount of percent. And then you as a sub turn this into the GC, and then he in turn elevates your your price by X amount of percent to cover for any unforeseen. Right. And then plus they've got their markup on that. So it's getting elevated three times before it gets to the owner. So the owner is probably paying three to four times more in a GMP than what they would if they just got three consecutive bids.
SPEAKER_00
So it's kind of like an insurance policy. They're willing to pay way more just to make sure it doesn't exceed
SPEAKER_02
well and and and you know the the the contractors and stuff, that you know, the the GCs, that they like the GMP workers, they make good money in it. And so what they do is like they go in, they've got a sales pitch. Now, you've got you're still bidding, but it's not a public bid. You know, it's it's a private bid. So with them going in, sitting down with their entity that they're bidding to, they're telling him, you know, like, hey, this is what we think it's gonna cost. We're gonna guarantee not to go above this amount. But if we come in, you know, just say they come in $100,000 under, some GCs are gonna say, we're gonna give you 50%, we're gonna keep 50%. Some GCs are gonna say, we're gonna keep 40%, we're gonna give you 60%. And this is where the entity that you're bidding to, that's where they decide, like, you know, well, they're gonna give me more money back, you know, I'm gonna try to go with them. Because that's that's just their grasp on things, like, you know, hey, this is our our way in, you know, we're gonna give back a little offer a little more money back, you know, to be able to get this job. You know, one GC may, you know, offer more than what the other two do or other three do. Which sounds dangerous. Well, it in a way it is, but there again, you know, going back to the question that was asked, uh well, in your question, you always walk about how dangerous it is, you know, it's it's very dangerous because it can very well go to the full GMP that was given, and then the entity that you bid to doesn't get anything back.
SPEAKER_01
Yeah,
SPEAKER_02
but you've got everything elevated so much in price, you're already making a mint, and then if you come in at a little bit less, you've still made a mint, and then you're this is a bonus for you.
SPEAKER_01
Okay. You know,
SPEAKER_02
you're you're getting you're getting you you may have you know 60% profit in this job,
SPEAKER_01
right? And
SPEAKER_02
then you're getting another you know $50,000 on top of that
SPEAKER_01
to boot. Yeah.
SPEAKER_02
To boot.
SPEAKER_00
So as a as a contractor on this type of job, uh you need to bid to account for things that are going to happen. You need to qualify your bid.
SPEAKER_02
Yes, qualify your bid. Yeah,
SPEAKER_00
that's kind of a good thing.
SPEAKER_01
But you're doing that anyway, hopefully on every bid. Yeah,
SPEAKER_02
right. But you know, you want to give as much or more detail as you can on a GMP because there's going to, like, like this person said, there's going to be stuff that is missed by the architect or by the G by the engineer. There's going to be stuff that's missed even by the owner. You know, the owner may say, you know, I decide I want to do this, this, or this. But anything that changes in your scope of work that was not on the drawings that you bid on, then you are 100% should be able to get a change order. Because you have done your due diligence, you have put this job in to the best of your ability based on a price that that you gave, based off of the drawings that you were given to price at that time. Now, here we are, we've got some changes, some stuff. You know, the city wants to see this. You know, the engineer architect's like, you know, well, we want to see this happen, you know, we missed it. Well, that's not your fault. You bid off the drawing, so I'm going to present you with a change order. I'm not going to charge you any more for the work that I bid on, but for this work that wasn't on the drawings, I need to get reimbursed for.
SPEAKER_00
So in that case, that's kind of outside the GMP.
SPEAKER_02
Yeah. It is. You know, you've got a GMP, but also in that GMP, they've got content your GC has set up a contingency pool. You've got a pool of money out here that's sitting for instances like this. Now, and what they do is like, you know, just say this is a courthouse that they're building, for instance, or a school that they're doing for the county. All right. They look at previous projects they've done with GMPs, and and that's what they kind of base it off of, you know, is like, well, this is what everything total start to finish worked out per square foot. Well, materials and stuff and everything's gone up, you know, 20% since I've done this one. So we're going to add 20% to that. So that gives them a good baseline of where they should come in. And so now we're going to use that baseline. We last job we done, we went over like 25% or 30% in change orders. So we're going to take this lump sum of money and we're going to add another 25-30% to it for change orders. If we don't use it, then we'll keep 50% and give 50% back to the county or the city, you know, whatever it may be. So I mean there's a lot of loopholes in a GMP in the entity you're bidding to, whether it's a county, city, individual, whatever it may be, they like the thought of like, hey, I know from start to finish this is all this project's going to cost me.
SPEAKER_01
Yeah.
SPEAKER_02
And so they're willing to pay more, and they may not realize they're paying more, but they're going to pay more for that sense of, you know, no change orders, where in realistic times, you know, in measures, if they would have gone with three bidders and wrote a handful of change orders, they still probably would have come out cheaper in the long run.
SPEAKER_01
Probably. And over time, after job after job after job, yeah. Yeah. You know, but they're they're looking at this instance and their their profit margin on this job, and that's that's all they're concerned with at the time. So yeah. Well,
SPEAKER_02
guys, it was kind of lengthy, but
SPEAKER_00
question answer. Question answer?
SPEAKER_01
Yeah.
SPEAKER_02
To the best of our ability.
SPEAKER_01
To the best of our ability. That's all we can do. That's all anyone can do. That's right. All right. Thanks, fellas.
SPEAKER_00
Yeah, man.
SPEAKER_02
Appreciate it.
SPEAKER_01
Jerry?
SPEAKER_02
Thanks for the questions. Please continue to respond and question and give feedback on uh our YouTube channel or our Facebook channel, on our Facebook, on our Profit Dig channel, anything. Wherever we're at.
SPEAKER_01
Everywhere you see us. Yeah.