The ProfitDig Radio Show
Practical talk for excavation and sitework contractors and estimators. Bid smarter, run the numbers, and keep more of what you earn.
The ProfitDig Radio Show is a straight conversation about the work and the business behind it. We talk through real jobsite situations, estimating and job costing, cash flow, equipment decisions, and the problems that show up when you are running crews and trying to make a profit.
If you dig, estimate, or run a sitework or excavation company, this show is for you. You will hear from the ProfitDig team and from contractors who do this work every day. No fluff. Just practical talk you can use on the next bid or the next job.
New episodes come out every week.
Learn more about ProfitDig, easy job bidding and costing for construction contractors, at https://profitdig.com
If the show helps you, follow it and leave a rating. That is the best way to help other contractors find it.
The ProfitDig Radio Show
Construction Takeoff: What Is It? (Part 1)
Use Left/Right to seek, Home/End to jump to start or end. Hold shift to jump forward or backward.
Construction industry veteran, Jeff Spencer, talks about construction takeoffs. Understanding exactly what you are bidding on is critical for performing a profitable job. As a construction company owner and professional project manager, Jeff tells you how he approaches takeoff. The guys talk about it while looking at some plans.
Subscribe, share the link, and learn from the ProfitDig guys!
ProfitDig - easy job bidding and costing for construction contractors. Low monthly fee. Cloud-based. No contract.
https://www.ProfitDig.com
How you want to approach beginning your takeoff? Um do you start by going, you know, one whole page at a time and calculating everything on a single page, or do you focus you know on some different type of method?
SPEAKER_01Welcome to the Prophet. Construction show. My name is Chris Work. I'm here with Jeff Given, Jeff Spencer, producer of Jerry Work this evening. Hello. How is everybody? How are we doing? Doing lovely awesome. Fantastic. Well, as always, trying to bring you the the the best content, some hot tips or quick tips as we like to call them for you guys getting started. I'm gonna turn the table over to you. Oh hey, while you're here though, go ahead and like the channel, like the video, subscribe to the channel, and like the videos, all the above. Guys, great to see you.
SPEAKER_00You too, man. Jeff Spencer, you and I were looking through uh this these set of drawings, and we were talking about how you want to approach beginning your takeoff. Um do you start by going, you know, one whole page at a time and calculating everything on a single page, or do you focus you know on some different type of method?
SPEAKER_02Well, I mean, everybody has different approaches. What I like to do is first thing I do is go in and look at existing conditions and demolition. You know, whether you're a GC bidding on the whole project or you're a sub, there still may be a scope of your work that's going to have demo in it. And if you're a sub, more than likely, if he knows that you're bidding the GC you're bidding to, if he knows you're bidding a certain part of this job, he's already looked at the demolition. He's gonna have it included in your scope, whether you know it or not. So it's good to go ahead and be proactive and find out if you have any kind of work. And if not, if it's something that's out of your wheelhouse, then go ahead and and exclude any demolition, put it in your exclusions, qualifications.
SPEAKER_00And so these drawings are real nice and they they specifically call out
SPEAKER_02every item that has to be.
SPEAKER_01Every
SPEAKER_00item that requires demolition.
SPEAKER_02You don't always have that either. I mean you're gonna have to kind of look at it and see.
SPEAKER_00So you just take your best guess at it, or it never hurts to follow up with uh
SPEAKER_02no. I mean, they'll always they'll always give you like something like may say typical. Like this was eat this one even says typical. So demolished fencing with uh within protect project limits, typical. So I mean they kind of give you a good outline of all the fencing and stuff here, uh, but it never hurts to make a job site visit.
SPEAKER_01That's right. I was gonna say, why not drive out there and take a look?
SPEAKER_02Yeah, yeah, you know that that fence that may be you know 20-foot-high chain ink fence.
SPEAKER_01I changes fence.
SPEAKER_02It may be a little goat fence. I mean, you never know. It may take a little more labor and a little more effort to get it down. You know, this particular job has several sinkholes and stuff you had to address, a pond had to be filled in, uh, and there again it gives you typicals. So you never really know without looking at it, you know, these are some pretty big areas right here. You know, how deep are those sinkholes? Yeah you know, what's it gonna take? You know, so you really need to ask for bore reports, you know, boar samples to see if they're quadritic, to see exactly what you're dealing with here, how much area you gotta do. You know, just because it shows this area right here, when you get done, that area may be that wide. It may be 40, 50 feet deep. You know, you never know until you actually get there and start working on it. Right. Uh, but qualify your bid. You know, like hey, these sink codes, you know, I'm I'm planning on going down X amount of feet, uh plan on using X amount of rock, plan on, you know, qualify your bid. You know, say, you know, this is anything other than what I've priced right here, we'll have to be addressed in a change order. I'm going at this point as far as I'm going.
SPEAKER_01Sure.
SPEAKER_02Now, the more information they give you, then of course the more you can go. But if you don't have that information, qualify your bid. You know, don't just say, hey, I'm going to do these sinkhole repairs for X amount of dollars, and it may take you two or three times that much to do it.
SPEAKER_01Yeah. Don't be afraid. Right. Yeah. Because you're probably not the only contractor who's doing that.
SPEAKER_02Right. So especially when it comes to sinkholes, I
unknownmean,
SPEAKER_02it's kind of like a uh a toss-up. You know, it's who knows the right answer. You know, nine times out of ten, it's not gonna be right until you get in there and start.
SPEAKER_01Toss up is that's a big structure.
SPEAKER_02Right. This is uh uh site layout. Site layout, your overview, your site layout here. This is what the project's supposed to look like when it's complete.
unknownUh
SPEAKER_02you know, a lot of times there's some some notes on there. You know, it's they they put pages in your plans for a purpose. Sometimes in your scope of work, all your notes may not be there, they may be on another page. So it's always good to look over everything and look at a quick glance to try to figure out, like this one right here, for instance, uh, gives you your site diet. You know, this particular project here is 88 acres, uh, almost 89 acres. Uh building setbacks. Uh gives you the address of the site.
unknownUh
SPEAKER_02but I mean there's there's a lot of information in there that you you may need, you know, from time to time. So, you know, don't don't just overlook it. Make sure there's nothing on there that's going to pertain to you.
SPEAKER_00So I noticed they gave you the back to back, they gave you the before and the after.
SPEAKER_02Right,
SPEAKER_01yeah.
SPEAKER_00Right off the bat, eye level.
SPEAKER_02Yeah. Now this right here, I didn't really print off any. This is a job that's already been completed. I didn't bring any grading drawings with me because I didn't bid on the grading on this project. Uh, just the utilities. Uh
SPEAKER_00but there was a set of plans here. Oh,
SPEAKER_02yeah, there was
SPEAKER_00removed before the came tonight. Right. All right.
SPEAKER_02Uh so this is what I was looking at, what I was interested in. Um they have a there's also another portion I didn't bring. There's a city portion of water line that had to be relocated and and added. Uh it was about a mile long of it, close to it.
unknownUm
SPEAKER_02first thing you do when you start your takeoff, take your scale. Always check your scale that they give you on your drawings and make sure it is right because sometimes your digitizers will skew drawings, or you've got it on a fit to page, and so it may bring your drawings out to be a different scale than what they're supposed to be. So check your legend first thing. Make sure that your drawings are to scale before you ever start.
unknownUm
SPEAKER_02next
SPEAKER_01and even note it on your sheets, right, as you're going through, because I mean obviously as the you know the depth changes from the drawings, so just maybe go ahead and just make a note so you don't even have to make the you know mistake of miscalculating that, yeah, you know, misreading it rather.
SPEAKER_02Right. And uh you asked me a while ago about page by page or item by item. Generally what I like to do is I like to take off my deepest, my deepest, excuse me.
SPEAKER_00Your deepest?
SPEAKER_02My deepest, my deepest uh utility first. So I generally start with my sanitary sewer because it's gonna be the one, and I'll tell you why I do that. It's got to go in regardless, it's gonna be your deepest utility. You're gonna have utility crossings, your other utility is gonna cross it. So at that point, you know, you may have sewer crossings just say right here on this this for instance. Well, at that point, uh I may have to figure in extra fittings because that sewer could be on the same elevation as what my water line is.
SPEAKER_01So you gotta go under it. So
SPEAKER_02I've got to take my water line under it, or over it, you know, whichever one works the best, but more likely you're gonna go under it, which there again requires fittings, it requires concrete for reverse kickers, rotting material. And just because you're not bidding on a storm drainer doing the the grade work, you need to look at the storm as well because there's gonna be conflicts from where you cross the storm, and you may have the same thing. So you may not think you need to print off the grating and and and drainage drawings, but if there's gonna be issues where you cross, you need to print them off and look at them because a job like this, like I said, you know, it was it was over a mile worth of pipe, and you may have several conflicts there, several fittings, and it's a big pipe, 10-inch pipe. You know, those double line fittings aren't cheap, and concrete's not cheap.
SPEAKER_01Money.
SPEAKER_02Money. And it can it can get you head in the wrong direction in a pretty pretty big hurry.
SPEAKER_01One thing I've learned, just from the time I've known you, which has been my whole life, pretty much by your in terms of uh your experience in construction. If you get your head in the wrong place in construction, it will screw you up, man. It will screw you over, okay?
SPEAKER_02Yeah.
SPEAKER_01Jimmy T.
SPEAKER_00Already.
SPEAKER_01I'm telling you.
SPEAKER_02Yeah. Yeah.
SPEAKER_01What are you gonna think about? You know, I mean, no, we're talking about a size, I mean, it's a sizable job, you know.
SPEAKER_02Almost a million square foot a building. A
SPEAKER_01million square foot ability, yeah. But even if I'm just getting started and I'm just doing some great work, or I'm just running some small residential, you know, project, putting in an underground utility, small mistakes adds up. It adds up really big. Yeah, yeah, quickly.
SPEAKER_02You think, you know, well, there's one, that's no big deal, and then there's two, well, that's okay. Third one, like, man, what's going on? Yeah. By the fourth or fifth one, it's getting in your pocket,
SPEAKER_01right? Yeah.
SPEAKER_02So, but anyway, back to what we were talking about on preferences of no, you good, boo. Of how to take off a job. All right, that page will just come through. That was that was the overall utility plan as far as the fire line and domestic water. Uh, I'll generally do a quick overview, you know, a takeoff of my main trunk line, and I'll write that down. Okay. Alright, so then I come in here, you can see I
unknowngot
SPEAKER_02some figures right here, but what I like to do is like if I've got 10-inch pipe, I'll write like 10-inch pipe. I generally, this is a little different. I generally like draw a line up under it and type 10-inch PVC, and I put my quantities down here and then total them up. 8-inch PVC line, quantities, total them up. 6-inch lines, fire hydrants, uh, 45s, T's, uh, PIVs, any kind of fittings that I may need is going to be listed out there, and then I'm gonna total them. And there's multiple pages to this project. So you got a match line here, I go next sheet, I take off that match line, do it, do the same thing. After I get through my three or four sheets, I go back and total everything up. That gives me my total quantities. I go back and look at my rough takeoff on the main overview. If I got some discrepancy, this helps me go back and find where it's at.
SPEAKER_01Identify it quicker.
SPEAKER_00Yeah,
SPEAKER_02yeah, I can I can figure out, you know, that hey, I'm I missed something on this page, I missed something on the next page, or whatever it may be, but this way it locks in my takeoff. Just because I got to take off the whole job written down, I don't know what area I made a mistake on. And so if I can figure that out, there may be something else there I need to look at. Why did I make that mistake? Right. What else did I not see? So I need to go back and take this one page it's off and slow down and see what's going on. And as we talked about while ago, conflict with existing or other utilities like storm drain, uh water, whatever it may be. Uh I don't know if you can see this on camera or not, but I kind of drew like an end view of your pipe that you may come in conflict with, and it's on the same elevation. That's what I was talking about. You got a 45 down, 45 over, 45 up, and then 45 back out. So you got to have reverse kickers that you got to key in to your your trenches with all thread rods tying to these 45s to hold them in place. And your bottom kicker, bottom 45s got to have kickers on them as well, or thrust blocks, whatever you want to call them, to keep them from blowing it.
SPEAKER_00And that's because it's just so much pressure when it hits it.
SPEAKER_02Right.
SPEAKER_01And I like how you've illustrated that on the sheet. Do you normally do that during the bending process while you're going over things? If you're like, hey, you know what? Just a friendly reminder, well, it didn't really apply here, I guess. But on the previous sheet, this was for demonstration. But would you do that on like when you're going over your plans? Sometimes. Do you see something? Would you like to see
SPEAKER_02what we're doing?
SPEAKER_01Sometimes I will
SPEAKER_02I will kind of sketch it out just to make sure I've got everything covered, and it will help me, you know, look back and say, you know, well, I just had one of these issues a minute ago, so I need basically the same quantities for this next one. Now, if the pipe you come in counter with is twice as big, that changes things. It changes things. Yeah.
SPEAKER_01Okay.
SPEAKER_02But yeah, it definitely, you know, it's something you need to look at because just because on topographical view and you're looking down through here, doesn't mean there's going to be conflicts, it's not showing the drawings. So you got to you kind of got to look at all aspects of the job from start to finish, from grading to to in storm drainage, all the way through, you know, sanitary, water, uh, fire line, whatever other utilities you have, gas lines could be an issue, fiber optic, you know, who knows what all's going in. But there's going to be you know encounters that you're going to have to deal with. And if they're existing, gas line, fiber optic, you know, any kind of telephone company you work with, power company, I mean
SPEAKER_00gotta go under them.
SPEAKER_02You gotta go under them because it's it's it's rare that you can get them to come out and and move their line.
SPEAKER_01Yeah. You
SPEAKER_00almost wouldn't even ask what I'd
SPEAKER_01say. So
SPEAKER_03we've got about 30 seconds left in this.
SPEAKER_01Oh, well, let's wrap it up here, guys. We'll come back. Yeah, that's been fun. Jeez.
SPEAKER_02Guys, I know we're not the best in the world at talking and putting stuff together, but hope this is good information that will help you out. Yeah, don't
SPEAKER_01believe me. Yeah, yeah. Tell you why. Yeah. If you have any doubt, just check us out at ProfitDig.com.
SPEAKER_02Yeah.
SPEAKER_01We offer an awesome construction bidding application. It's only $99 a month. Uh, it can help you out when you're putting your bids together, speed up the process, uh, make you more efficient and effective. Um, Jeff Gibbons, thanks as always. All
SPEAKER_03right,
SPEAKER_01Jeff. Thank you, man. See y'all next time.
SPEAKER_02See y'all