Practical talk for excavation and sitework contractors and estimators. Bid smarter, run the numbers, and keep more of what you earn.
The ProfitDig Radio Show is a straight conversation about the work and the business behind it. We talk through real jobsite situations, estimating and job costing, cash flow, equipment decisions, and the problems that show up when you are running crews and trying to make a profit.
If you dig, estimate, or run a sitework or excavation company, this show is for you. You will hear from the ProfitDig team and from contractors who do this work every day. No fluff. Just practical talk you can use on the next bid or the next job.
New episodes come out every week.
Learn more about ProfitDig, easy job bidding and costing for construction contractors, at https://profitdig.com
If the show helps you, follow it and leave a rating. That is the best way to help other contractors find it.
How Are Construction Bonds Beneficial For Contractors?
•ProfitDig LLC
Use Left/Right to seek, Home/End to jump to start or end. Hold shift to jump forward or backward.
0:00
|
7:04
A construction bond protects your clients if problems develop with your work. The types of bond include bid, performance, payment, maintenance and supply bonds, among others.
In this video, Jeff Spencer explains the difference of bidding bonds and payment and performance bonds.
ProfitDig - easy job bidding and costing for construction contractors. Low monthly fee. Cloud-based. No contract.
So you this is while you're in the process of doing the job.
SPEAKER_01
While you're doing the job, yes.
SPEAKER_00
And you're paying this every month.
SPEAKER_01
Every month.
SPEAKER_00
So Joe Spencer, we were talking about the different types of bonds that we have. And you know, you were talking about the bid bond, and you were talking about the payment and performance bond, your P and P bond. Can you talk a little bit about the difference between those two types of bonds?
SPEAKER_01
Well, your uh uh bid bond is just like to to protect you in a bidding process. So if you're looking at like a government type job, uh maybe it's you know DOT work, maybe it's municipality work, but they require like a in in state Tennessee they require a 5% bid bond. What that does is that protects you and it also protects the entity that's that's requested the bids. So if I default on my bid, you know, after I bid a project, in other words, if I start second-guessing myself, I missed something or I didn't put good numbers together, or maybe I realize, you know, that I was you know 15-20% lower than the next bidder, you know, I might start, you know, what I leave out, what I miss. So I may decline the bid. I may want to back out of it. So what that bid bond does, it covers the owner, and it also covers you because it takes a lot of FD off you to where they go to second-place bidder. And so, whatever the difference is, your bid bond has to eat that difference. Your insurance company does to make it work out to where they can get their second place bidder to come in and do the job at a higher rate than what they thought they were getting.
SPEAKER_00
So if it's a $15 million job and you bid it, you bid it at $10 and everyone else bid it at $15,
SPEAKER_01
that $5
SPEAKER_00
million gap there. Your
SPEAKER_01
bid bond's gonna cover that.
SPEAKER_00
And you're only responsible for paying 5% of what you bid or what the uh the next person bid.
SPEAKER_01
Well, 5% of the, you know, I'm gonna I'm gonna pay. Or the difference. The difference is
SPEAKER_00
the five million dollars between you know 15 minus 10 and 5. So you take 5% of 5
SPEAKER_01
million's gonna pay that, I'm gonna pay the 5%.
SPEAKER_00
You're gonna pay the 5%, they're gonna pay the 5,
SPEAKER_01
yeah,
SPEAKER_00
and you're gonna pay the 5%.
SPEAKER_01
Yeah.
SPEAKER_00
Okay. Now, does that impact your I guess uh your credit with the the company, the insurance, the bid company,
SPEAKER_01
it does, yeah.
SPEAKER_00
Bond company you're working with. Yes.
SPEAKER_01
So
SPEAKER_00
that next job that comes around, like maybe your rate's higher this next time. Yes,
SPEAKER_01
very possible, yeah.
SPEAKER_00
Okay. And now, what is a payment and performance bond?
SPEAKER_01
Once you get under contract and you start a project, so you get 25, 30%, you know, complete with a project, you decide that you know this project's not gonna be feasible for you for some reason, or you can't, you know, maybe you don't have the labor or the equipment you need to do this job, maybe it's bigger than what you thought. Uh you may decide to back out or decline then. So that gives your your insurance company has to pay you know a portion of what it's gonna cost for that company to go ahead and find someone else, maybe the second place bidder, maybe a you know, a totally different contractor that didn't even bid on the project to come in and complete your work that you did not finish.
SPEAKER_00
So you this is while you're in the process of doing the job.
SPEAKER_01
While you're doing the job, yes. Once you're under contract, yes.
SPEAKER_00
And you're paying this every month.
SPEAKER_01
Every month. And so, you know, if you've just say, you know, if if I'm an estimator and I like you know this particular project, say I think it's gonna take six months, you know, to do the job. Well, if we go into seven, eight, nine months that goes over what I thought you know was gonna do, then you still got to pay that P bond at you know, 1.25%, you know, whatever it may be, you know, whatever deal your bonding company's got with you,
SPEAKER_00
yeah,
SPEAKER_01
you know, there again that's costing you money because you have gone outside your grace period, so the bond should stay in place, so you've got to continue to pay it.
SPEAKER_00
Yeah, and one of the things we were talking about is you know, some you know, external force causes you to take longer than normal, and you have to issue a change order, like too like one thing you mentioned was rain days, like excessive rain days. Well, you just can't do the work on those days. Now you have the option there of uh or issuing a change order for that. Maybe do you just do it for that bond or you include everything that's affected by the rain days? Well,
SPEAKER_01
it's not just for the bond, but also to because a lot of times your your jobs are tied to liquidated damages. Like if you've got you know 120 days or 200 days, whatever it may be in this particular job, uh if you go over that, it may be a thousand dollars a day, fifteen hundred dollars a day, five hundred dollars a day, whatever the liquidated damages are. So, in order to avoid those, if you have you know inclement weather that keeps you from performing your scope of work, you need a changeover to increase those days. You know, that way extend your time period so you're not having to worry so much about liquidated damages. Uh so that's why it's good, you know, for your guys in the field to always keep a record, keep a daily log. We haven't talked about that much, but it's very important, you know, for your forums in the field and your superintendents to keep a daily log per job, you know, what's going on, how many rain days you had, and I can't remember now what the standard is here in Tennessee, but I think they allow for like you know five or seven days a month, you know, rain days on average. So theoretically that's included into your original contract. So if you've got you know 15, 20 days, you know, rain days, that is a good plausible uh argument for extending your time frame because you know, hey, we've had you know seven, eight days longer than what was anticipated per month in rain delays.
SPEAKER_00
Well, good information just fans.