The ProfitDig Radio Show
Practical talk for excavation and sitework contractors and estimators. Bid smarter, run the numbers, and keep more of what you earn.
The ProfitDig Radio Show is a straight conversation about the work and the business behind it. We talk through real jobsite situations, estimating and job costing, cash flow, equipment decisions, and the problems that show up when you are running crews and trying to make a profit.
If you dig, estimate, or run a sitework or excavation company, this show is for you. You will hear from the ProfitDig team and from contractors who do this work every day. No fluff. Just practical talk you can use on the next bid or the next job.
New episodes come out every week.
Learn more about ProfitDig, easy job bidding and costing for construction contractors, at https://profitdig.com
If the show helps you, follow it and leave a rating. That is the best way to help other contractors find it.
The ProfitDig Radio Show
How To Handle A Job Takeover in Construction?
Use Left/Right to seek, Home/End to jump to start or end. Hold shift to jump forward or backward.
A takeover occurs when one company makes a successful bid to assume control of or acquire another. Jeff Spencer, Chris Work, and Luke Fielder, talks about the process of job takeover in construction.
ProfitDig - easy job bidding and costing for construction contractors. Low monthly fee. Cloud-based. No contract.
https://www.ProfitDig.com
Uh pretty good topic here, like how to handle a job uh that you come in to take over once it's in progress. This can be true. Good evening again everyone. This is Chris Worker Procadine. I'm sitting here with Luke Filler, Jeff Spencer. Any Amenville?
SPEAKER_01Good? Guys
SPEAKER_00we talked about it earlier. Pretty good topic here. Like how to handle a job that you come in to take over once it's in progress. This can be tricky.
SPEAKER_01You can,
SPEAKER_00yeah. And you generally seem to have a roadmap to help our viewers. So
SPEAKER_01I think Luke is in a position right now where he has uh come into this particular topic, you know, on a couple of different projects, and
SPEAKER_00yeah,
SPEAKER_01you know, it's tricky. You know, what do you do? How do you handle it? Well, you're at a disadvantage off of that because the contractor that was there before you were, he had a good set of drawings he gave a bid off of, and he's got progressive payments, you know, as a work he's he's completed over time. Well, he breaches his contract or whatever, you know, they come to disagreements with him, the owner, he's out of the picture. Well, now Luke comes into play. When did Luke come here and finish his job? You know, how are you gonna price it? Well, I don't know exactly what Luke's strategy was or how he went about it, but in my personal opinion, you know, is like there's only two ways to do this. Either you do a have your surveys do another toe pool, engineers give me a new set of drawings based off of what work's been done, I'll bid that work based off of what is left to do. And Luke brought up a good point here in a minute, we'll get to just a second. And the other way is, you know, the only fair way to do it is like tying materials. You know, because Luke is at a disadvantage. He has no idea what material has been moved and what material likes to be moved.
SPEAKER_00Right.
SPEAKER_01It could be import. You know, the original drawings may have shown, you know, like an export job. But they may have wasted dirt, took dirt off this job to use it on another job, and may have may have overused that job. And so now it took off more material once you got left, so now it's actually import jobs to the export job. That's one thing you do in the grading business. You know like when you got a job in this general area, it's an export job. Well, when you got a job bidden in a decent you know proximity, you know, five, six, seven miles away, it might be an import job.
SPEAKER_00Got that material you can
SPEAKER_01do.
SPEAKER_00Got that material.
SPEAKER_01You can sell material off this job and buy it on this job. So you can actually, you know, double your money from one job to the other. You know, that may have been what they've done. You know, they may have overloaded one job from the other and over exerted it, and then Luke doesn't know that. Exactly. But if he came and looked at a job, and it was, you know, just say a job you know, he's like 70% complete, you know, the the owner's paid out 70% of his money for what he's got in his budget. Well, all right, Luke, I'll turn on you now. I mean, we talked about the stakes a while ago. You went and looked at the project and
SPEAKER_02it
SPEAKER_01was supposed to have been primarily degrade, right?
SPEAKER_02Well, yeah, they're supposed to tie it in on, you know, obviously on the new proposed contour lines, they're supposed to tie it in to natural ground. The uh stakes that I saw at the very end stakes was three and a half foot cut at existing ground where it was supposed to tie it in.
SPEAKER_01Yeah,
SPEAKER_00true. Yeah, exactly.
SPEAKER_02And so, you know, and then also on top of that, you also had, you know, like you said, the amount of material that they've already hauled in that I have no idea how far they are off of what existing ground was.
SPEAKER_01Yeah. So, you know, there's really no fair way to do it. Like I said, there's only two ways to do it. That's a new toehoe, new set of drawings, and you go to bid based off those drawings, whether it be import or export, you know, it is what it is.
SPEAKER_00Right.
SPEAKER_01If the if the owner has overpaid his initial contractor, that's a deal he's got to work out with them. It might be a lawsuit, you know, whatever it may be. But you know, he's got to get his money back, you know, to be able to pay someone like Luke to come in and finish your project. And the other only other frame, you
unknownknow,
SPEAKER_01fair way to do it for both parties is time materials. Because as a contractor, you've got your set rates for your equipment, you've got your set rates for your men. That's covering overhead, that's covering your fringes, that's covering like workers comp, and then a profit.
SPEAKER_00A
SPEAKER_01profit margin.
SPEAKER_00And the materials are the same. Yeah,
SPEAKER_01materials are the same, yeah. But you know, and there again, you need to, you know, have someone, it shouldn't be up to Luke to go out and survey his job to put in a bid. The owner should be able to give him enough information, like, you know, if there's 5,000 feet of sewer on his project, how many feet's been put in?
SPEAKER_00Right. How
SPEAKER_01much have you paid for? If he's paid for, you know, out of that five thousand feet, he paid for four thousand feet, well Luke was there and looked like, well, I don't think that's right. You know, it looks like it's only like you know 2,000 feet in.
SPEAKER_00So
SPEAKER_01you know you got a thousand foot bus right there somewhere.
SPEAKER_00Yeah.
SPEAKER_01So you know you gotta you gotta figure that out. But, you know, there again, if it if they don't want to go to the problem or the the pain of having a survey to come in and engineer to redesign it, like, hey, you know, I don't know how I can do this is tile materials. I'll give you my hourly rates and this is what it'll be. We'll work those jobs done or to get it right out of the way.
SPEAKER_00Right.
SPEAKER_01Yeah,
SPEAKER_02yeah. And that's that's pretty much why I kind of work this bending out, is just uh there there is still some material there that uh and I'm just gonna act like that's the that's there's enough material there, and then any added extra material that's that's just gonna be a change order. Um because they they they didn't really act like they wanted to kind of go for a go to go do a new topo, you know, give me a new set of plans or anything. So that's gonna be the only if you don't want to do time material, this is this is how it's gonna have to be done if that's the case.
SPEAKER_00Right. Right.
SPEAKER_01It'll be a change order.
SPEAKER_00Yeah,
SPEAKER_02exactly. And so whatever any time extra time, you know, that's improved for for that amount of time that's gonna have to be for the change order, that's what they're gonna have to pay for.
SPEAKER_00And that'll
SPEAKER_01work, but you gotta be diligent. You gotta you get to that point, you gotta stop.
SPEAKER_02Oh yeah, for sure. Yeah,
SPEAKER_01don't let them talk again if you know continue on,
SPEAKER_02get
SPEAKER_01that interview. You
SPEAKER_02know,
SPEAKER_01uh
SPEAKER_02this
SPEAKER_01point only for X amount of dollars.
SPEAKER_00Yeah.
SPEAKER_02For sure.
SPEAKER_01Yeah.
SPEAKER_00Well, that's good stuff, Ellison. Thank you so much. Jeff G
SPEAKER_01you got a question or something?
SPEAKER_00Oh, Jeff G, our engineer this evening. Yeah, man, yeah. Hey.
SPEAKER_03Um I was wondering about like the kind of the tangential risk to taking on a job over for someone else. Um let's say you took over a job and um you weren't aware of how shoddy the work was.
SPEAKER_01Well, that's a good point. So if
SPEAKER_03you do a very poor job and you're coming in afterwards, do you risk putting your name on a job that someone from the outside may not realize that? Oh, well, you know what half of that job was done by you know these goofballs over here, LLC, and then this other half was done by TriStar Land Solutions.
SPEAKER_01But
SPEAKER_03you risk your reputation there, or the opposite way. If you come in and
SPEAKER_01you give it to
SPEAKER_03you fix it, does that give you a huge advantage?
SPEAKER_01Well, it could, but the main thing is to protect yourself up front. That's a very good question, Jeff. I'm glad you brought it up. Because, you know, like if if they've got X amount of road that's built or building pads, I need to see their test reports. I need to make sure that they was at, you know, if it's 95% compaction, or if it's 100% compaction, whatever the requirement job, I need to see the test reports, what they've done, because when I get done, this road's gonna be mine. I've got to warranty this road for a year. I've got to warranty the building pads for a year. You
SPEAKER_03gotta warranty their section, too. Their
SPEAKER_01section, yeah. And another thing, like on utilities, you know, that's that's that's even more crucial than the than the grade work. You know, if they got a bunch of water line in, a bunch of sewer line in, you gotta go back to test some of us at work, yours may pass five. But when you start testing theirs if it hadn't been tested, you may be digging up stuff and fixing stuff from here to to the end of time.
SPEAKER_02Right. Yeah, well that's where exclusions come in.
SPEAKER_01Right. Well,
SPEAKER_02yeah, where you dream. And I that's one thing that uh definitely one thing that I included in mind.
SPEAKER_00Absolutely.
SPEAKER_02Any prior work before my
SPEAKER_01buttons? That's a very good question. I can't believe we didn't touch on it, but yes, that's a very big concern. Well,
SPEAKER_00it's kind of the opposite. I was thinking like how you might use this as an advantage to develop that new relationship if you come in, but hell, if you if you come in and are actually able to turn the job around and make some money and move on to the next one, then yeah, you develop that relationship if you get out unscathed.
SPEAKER_01But and you know, initially, long in end game, yeah, you know, they're gonna appreciate your your hard work and get to the point you got to.
SPEAKER_00Yeah.
SPEAKER_01But when the owner has already paid for a product and they find out it's a shoddy product, and now you gotta go back and make repairs and do work, it's it's a hard bargain to sell.
SPEAKER_00I'm not sure. So they they've already had this bad taste in their mouth and factor, right. And now here they go
SPEAKER_01back and spend the money on again.
SPEAKER_00Yeah, exactly.
SPEAKER_01And then which it trickles down to the to the property, I mean to the to the new property owners. Because the developers, they're gonna take this property, they're gonna lease that or sell it to someone else.
SPEAKER_00Right. Well,
SPEAKER_01whatever cost they incur, they're still gonna pass it on down the road to them.
SPEAKER_00Right.
SPEAKER_03As a GC, is there any method to protect yourself against that situation? Well, it's like
SPEAKER_01you're talking about like exclusions, and you know, you've got to really read through your contract and your agreement, you know, to make sure that they're incorporating your exclusions and stuff, you know, what you agreed on. And you know, anytime you do a contract, if you can, try to always incorporate your bid proposal with your exclusions as an exhibit A, B, C, D, whatever exhibits they have in there, let yours be the last one. Just get them to include your bid proposal with your exclusions as an exhibit in the contract, and then you are somewhat protected. Now, you know, you have some contractors that will send out a 300-page contract. There's no way you can go through all that amount of time, you know, and look at it. Most of it's border plate stuff anyway.
SPEAKER_00Sure.
SPEAKER_01You know, you want to look at your special conditions, you want to look at your scope of work, look at your liquidated damages, and look at you know anything that may pertain to the work that you're doing yourself. Now, as far as payment, insurance, you know, that type of stuff, you know, those are border plate. Everybody has to comply with the same thing. Uh so you know, just know your contract, know your GCs you're dealing
SPEAKER_02with.
SPEAKER_01And you know, once you have three or four or five GCs that you trust, I would recommend focusing on those GCs. It's okay to pick up one every now and then, but you know, you need to do your research and make sure you know they're a reputable company, you know that you can get paid on, and they're not willing to, you know, they're not trying to take advantage of you up front.
SPEAKER_00Yeah. Does that make sense? Well, fellas, I appreciate it. Yes,
SPEAKER_01sir.
SPEAKER_00It's good knowledge.com.