Practical talk for excavation and sitework contractors and estimators. Bid smarter, run the numbers, and keep more of what you earn.
The ProfitDig Radio Show is a straight conversation about the work and the business behind it. We talk through real jobsite situations, estimating and job costing, cash flow, equipment decisions, and the problems that show up when you are running crews and trying to make a profit.
If you dig, estimate, or run a sitework or excavation company, this show is for you. You will hear from the ProfitDig team and from contractors who do this work every day. No fluff. Just practical talk you can use on the next bid or the next job.
New episodes come out every week.
Learn more about ProfitDig, easy job bidding and costing for construction contractors, at https://profitdig.com
If the show helps you, follow it and leave a rating. That is the best way to help other contractors find it.
Use Left/Right to seek, Home/End to jump to start or end. Hold shift to jump forward or backward.
0:00
|
8:20
Jeff Spencer, Chris Work, and Luke Fielder discuss the purpose of addendums in a construction contract, especially during the bidding process. Jeff also gives advice on what contractors should do when addendums affects their scope of work.
Addendums are frequently used in construction contracts, as they allow for changes to the initial contract without having to completely rewrite the document.
Check out this podcast, be protected, and be informed about the importance of this document.
Teacher Children of America. Uh okay. Hey guys, first we're gonna pop the look filler. Just going on, fellas. I like it. I like it. I like it. Well listen, uh, always trying to bring you the best content. We hope it's useful, help you grow your business. And these guys had some good discussions earlier on addendums. So I'm gonna let these fellas here take the floor and see if we can't get you guys in the right direction. Jeff? Luke?
SPEAKER_01
I know you're you're new to the business. Not new to the business, but new to being a uh construction owner. Right. Have you come across any bids yet that have addends coming out?
SPEAKER_02
Not yet. No.
SPEAKER_01
It's coming. It's
SPEAKER_00
coming. Yeah,
SPEAKER_02
it's coming. I'm sending the term.
SPEAKER_01
Yeah. And a lot of people, you know, new to the business, don't really understand or know about addendums, but addendums are you may have multiple addendums on one project, like in the business stages. You know, you may prepare your bid proposal based off of these documents they've given you today. You got, you know, say 80-85% complete plans. You bid that job, which 85% complete drawings, you
SPEAKER_02
know,
SPEAKER_01
are that's that's yeah. Yeah, right. That's that's a hard bid, you know, scope of work right there.
SPEAKER_00
Yeah.
SPEAKER_01
Well, the engineers are still, you know, working on this thing, architects, you know, they're working on it, you know, to progress it and get to where it's a more feasible project for the owner, whoever the owner may be. Well, after you give your hard numbers, you know, there may be an addendum coming out either before you submit that bid or shortly after you submit that bid. Maybe addendum one. Well, they made a few changes. At that point, addendum one overrides every other document that you had previously. That's why it's important, like when you bid proposals, to always classify in your bid proposal that your bid is based off of documents, which is your drawings, give your sheet numbers, whatever sheet numbers you're bidding off of, always list your sheet numbers and the date they were printed, the date they were given to you. Or not given to you, but the date they came out. So just like right now I said the 11th of July. So if I got a set of drawings today with an addendum on it, these are new drawings, and they're dated the 11th of July. That's what my new bid proposal is gonna say. This bid is based off of documents presented to me on July 11th, 2022, sheet numbers C 6.0 through C 8.2, whatever it may be. So that way there's no blind areas, everybody knows exactly what documents you bid off of, what your bid is based off of. So even at doing that, you may get another denim, a denim too, a denim two comes out. Always put on your bid that you have recognized and received a denim too. It may not have anything to do with your scope of work, but you still need to recognize, hey, I've seen this addendum, my prices are still good. If it does affect your scope of work, then you revise your bid based off the denim, the plans date that day, because it's gonna be a new date. It may be 7, 14, 2022, whatever that date may be. You revise your sheet numbers, your bid date, I mean your plan date, and revise your bid and resend it. But every addendum you get that affects your scope of work replaces the addendum before or the original set of drawings. So everything you're doing is based off of addendum two drawings at that point. Or addendum two information. So to protect yourself, make sure when you get addendums, you look at them and make sure that it does not comply to your scope of work, or if it does comply to your scope of work, make sure, because sometimes it requires a whole nother takeoff.
SPEAKER_02
Yeah. You
SPEAKER_01
know, you're like you're starting over. You know, and you may have to start over on a whole project to find out exactly what has changed, and you may not know what's changed until you do a complete takeoff. But that's protects you and the owner. Last thing you want to do is go into contractor work, you're trying to initiate one, two, three change orders because you did not review your addendum drawings, but now you give them numbers and they've held your feet to the fire and you're under contract now.
SPEAKER_02
Yeah,
SPEAKER_00
I was gonna say, I mean, you've lost any leverage you might have.
SPEAKER_01
Yeah. And so always qualify that stuff in on your bid, you let them know that you've seen up to addendum three. There may be addendum five out there, but this is all I'm bidding on is addendum three. And they're like, hey, we really like your numbers, we want to use you. Let me get you the last two addendums, you look at them and revise your bidding your bid accordingly.
SPEAKER_00
Is there any opportunity for the contractor in say in your shoes, you've bid on three, but you sort of have a gut feeling there's gonna be a four or a five. Are you sort of thinking ahead when bidding on three, or are you just strictly looking at what's in front of you?
SPEAKER_01
Well, you see things in the drawings that are like, you know, it doesn't make sense. Okay. So you're
SPEAKER_00
already forward-thinking at that point. You're already coming in my ass for what might be coming out. Even
SPEAKER_01
if it's your first goal range, like, you know, I'm pretty sure it's gonna be it doesn't come out because you know what they've got doesn't make sense.
SPEAKER_00
Yeah.
SPEAKER_01
But and that's another key point, too, you know, is like whatever you see, you know, and I call it, you know, uh uh contractor logic, you may be able to foresee something that the engineers made a mistake on. Don't bid a job like you see fit. You bid according to the drawings that have been given to you at that time. Okay.
SPEAKER_00
Because
SPEAKER_01
everybody else has been on the same drawings. And so you can you can bid yourself out of a job in a hurry if you try to start to make corrections to the engineer's drawings.
SPEAKER_00
I gotcha.
SPEAKER_01
If nobody corrects them or makes changes, at that point, if you're awarded the contract, and then anything that's done outside of your scope of work will be a change order.
SPEAKER_02
Right.
SPEAKER_01
And so that's what change orders are for. Uh because engineers, and I've said this before, engineers and architects, in my opinion, they shouldn't sit foot into an office if they spent five years in the field working.
SPEAKER_02
Yeah, that's hell in your head. Yeah, yeah.
SPEAKER_01
Yeah,
SPEAKER_00
yeah.
SPEAKER_01
But uh, you know, engineers are great, they get a good education, but as far as you know, field experience goes, uh a lot further than what you think.
SPEAKER_02
Yeah,
SPEAKER_00
you
SPEAKER_01
know, there's a lot of people out there that hold positions right now that calls for a college degree that never did get it because they had the field experience it took
SPEAKER_02
to get
SPEAKER_01
them to that position.
SPEAKER_00
Yeah,
SPEAKER_01
and so you know, physically doing the work and understanding the work will get you a lot further than a degree if you don't understand the work you're you're working on.
SPEAKER_00
Absolutely, absolutely.
SPEAKER_02
Yeah.
SPEAKER_00
Well, fellas, you got anything to add to that?
SPEAKER_01
Luke?
SPEAKER_02
No. No?
SPEAKER_00
Yeah. Alright,
SPEAKER_01
hey guys, again, Luke, tell us the name of your company one more time.
SPEAKER_02
Tri-Star Land Solutions LLC.
SPEAKER_00
That's right. So if you're in the middle Tennessee area, that's your service area right now. Yeah. So if you're in middle Tennessee and looking for some dirt, well.
SPEAKER_01
You have a new guy that's got a lot. Yeah, he's not just a new guy to the field. No.
SPEAKER_00
He's
SPEAKER_01
been over 20 years' experience in a grading in the excavation business.
SPEAKER_00
Yeah.
SPEAKER_01
So you're not getting a rookie. I mean, you're just getting someone to start a new business.
SPEAKER_00
That's right.
SPEAKER_02
Yeah. I've been in uh almost 20 years.
SPEAKER_01
Okay. Yeah.
SPEAKER_02
Oh,
SPEAKER_00
almost 20.
SPEAKER_02
Just a hair over 19.
SPEAKER_00
Yeah, there you go. Yeah,
SPEAKER_02
so
SPEAKER_00
awesome. Yeah. Well, check them out. Yeah. Tropfitdig.com. Yeah, Google Tri Charlotte Solutions.