The ProfitDig Radio Show
Practical talk for excavation and sitework contractors and estimators. Bid smarter, run the numbers, and keep more of what you earn.
The ProfitDig Radio Show is a straight conversation about the work and the business behind it. We talk through real jobsite situations, estimating and job costing, cash flow, equipment decisions, and the problems that show up when you are running crews and trying to make a profit.
If you dig, estimate, or run a sitework or excavation company, this show is for you. You will hear from the ProfitDig team and from contractors who do this work every day. No fluff. Just practical talk you can use on the next bid or the next job.
New episodes come out every week.
Learn more about ProfitDig, easy job bidding and costing for construction contractors, at https://profitdig.com
If the show helps you, follow it and leave a rating. That is the best way to help other contractors find it.
The ProfitDig Radio Show
Construction Billing and Cashflow Management Strategies So You Don't Get Wiped Out
Use Left/Right to seek, Home/End to jump to start or end. Hold shift to jump forward or backward.
Construction expert Jeff Spencer describes a strategy for managing your billing and cashflow that insures that at the end of the project all the bills are paid and you still have profit left over.
He also talks about the great danger of being too dependent on a single source of work, which was a bad mistake his company made years ago.
From ProfitDig - easy job bidding and costing for construction contractors.
https://www.ProfitDig.com
You always sort of keep this buffer in the future.
SPEAKER_01Keep the buffer in the future. That way when I get down to my last two or three months, I've generally got my cost plus 25-30% profit left over at the end.
SPEAKER_00Okay.
SPEAKER_01So that way I get to reap the benefits. I've paid my bills, I've paid my men, I've paid my equipment, I've paid my fuel, made a little bit of money throughout this project, and then at the end, I get this one big balloon payment because I have staggered my payments enough to where I've got a good sum of money, money left over at the end of the job.
SPEAKER_00How about it? How about it? Hello, America. Thank you for joining the Prophet Dead Construction Show. My name's Chris Work. I'm here with my partners Jeff Givens, Jeff Spencer, and our partner and producer Jerry Work. Hello. Oh wait,
SPEAKER_03I'm from a Michael.
SPEAKER_00Oh jump into some jumping shirt or something. But no, that's okay. Listen up. Make sure to follow us. You can find us on YouTube and all other major social channels. Give us some feedback. Let us know what you guys want to talk about. We're always we have all sorts of things to cover here, but certainly if there's anything specific you would like to discuss, then we certainly want to make sure we do that. Welcome, boys.
SPEAKER_01Welcome. Pop the topic. Sorry?
SPEAKER_00No, that's great.
SPEAKER_01Yeah.
SPEAKER_00That's great. I think it sort of makes the it sort of sets the tone.
SPEAKER_01Yeah, I thought the intro would be a good tab to pull a tab on it. Yeah.
SPEAKER_00Absolutely. Well, guys, we were having a discussion just a few moments ago, and Jeff, you had some some insight on overbuilt and how and how you might combat that, I presume.
SPEAKER_01Well, and and like past experience, you know, one thing that's always come to haunt us is you get overzealous starting a new project. You know, you get your store materials, you mobilize, you want to build for that, and you're like, you know, well, it may be a little half a month, month, you know, longer, getting started than what we thought. Let's go ahead and build a little bit extra and uh, you know, kind of have a good pad to start with. Well, it all, you know, that's all fine and good, but what happens is throughout the project, if it's a five, six, seven, eight-month project, want to end theirs, you know, you've already billed for the majority of your money. So you get down to the last two or three months, and it's like I can't bill as much as I need to because I overbuild up front. And so now here I am, I'm spending all this money paying labor and equipment and you know, some materials to get this job finished and put in that I'm not gonna get revamped for because I build up front.
SPEAKER_00Right. Well, what difference would that be by billing too much up front versus a final billing at the end if I had properly managed my finances throughout the project? Or are you saying it's just more difficult to do that?
SPEAKER_01Well, it's not more difficult. I mean, because you've built that money up front, but instead of taking that extra money and dedicating it to this job, like putting an escrow account or something, you've used that to fund other projects, or you've used that to pay, you know, past you bills.
SPEAKER_00Okay.
SPEAKER_01You know, you've used that money up. So now you're primarily working for free because you've already pre-billed this and got compensated for it, and you have nothing to show for it. So one thing that I've tried to do in the past, you know, over the last several years, I try to be kind of conservative. I look at my cost for this month, materials, labor, and equipment. I bill exactly what that cost is plus five percent.
SPEAKER_00Okay, so you you always sort of keep this buffer in the future.
SPEAKER_01Keep the buffer in the future. That way, when I get down to my last two or three months, I've generally got my cost plus 25-30% profit left over at the end.
SPEAKER_00Okay.
SPEAKER_01So that way I get to reap the benefits. I've paid my bills, I've paid my men, I've paid my equipment, I've paid my fuel, made a little bit of money throughout this project, and then at the end, I get this one big balloon payment because I have staggered my payments enough to where I've got a good sum of money left over at the end of the job when I've got to go back and do punch list items, I've got to, you know, adjust hydrants, you know, backfill behind the curve, whatever I've got to do, I've got money in there to compensate for that with a really, really good profit margin.
SPEAKER_00And so it sounds to me too, like that was sort of by overbilling, you're essentially mudding the books along the way. Exactly. It makes it harder to know where you're profitable or not and how to adjust that moving forward.
SPEAKER_01But when you get in that mindset, you know that you're doing that on a regular basis, then that tells me that that's when you need something like profit dig to help you manage your books because you may not have enough money in your project to be profitable from start, you know, from point A to point B, from start to finish.
SPEAKER_00Yeah.
SPEAKER_01And so if you're upside down off the start to where you're having to over-build up front to pay your bills, that's when you really need to look at you know how you've got your business structured and figure out, you know, hey, what do I need to do to change this? And what kind of application do I need to help me to keep guidelines on it? Sure.
SPEAKER_00And odds are it's not the first time you've done that
SPEAKER_01to
SPEAKER_00be in that position.
SPEAKER_01Exactly.
SPEAKER_04Yeah.
SPEAKER_00Constantly and catch up.
SPEAKER_01Right.
SPEAKER_04Yeah.
SPEAKER_01So that was the only point I was making in our previous discussion was you know, need to be cautious. Then the the worst fit in the world is get down to the last couple months of a job and and you build for you know 95% of it. Yeah. And you don't have any money left, so you're paying out of your pocket right now because you have overbilled and overspent.
SPEAKER_00Yeah. Mismatched stuff.
SPEAKER_01Yes. Yeah.
SPEAKER_03Have you ever done that?
SPEAKER_01Yes. That's how I got to this point. That's where. Yeah. That's why that's what I'm saying. It's not it's it's not it's not a good experience, you know.
SPEAKER_03Was that something you did earlier in your career?
SPEAKER_01It was something I did later in my career to try and offset desperate times.
SPEAKER_03Okay.
SPEAKER_02You're robbing Peter to pay Paul.
SPEAKER_01Exactly.
SPEAKER_00Yeah.
SPEAKER_01Yeah. Yeah.
SPEAKER_00Ended up chasing your tail.
SPEAKER_02Was that pressure from your management coming down, or was that just a personal pressure you put on yourself?
SPEAKER_01Well, it was, it was, it was a timing issue. It was like we had done good up to a certain point, and then economy crashed, 2009.
SPEAKER_00Oh yeah, bottom fell out.
SPEAKER_01Yeah, bottom fell out. And so you start grasping straws. And so we start overbilling, overbilling, overbilling, you know, trying to to make things work. And then, you know, before you know it, the guy you're working for files bankrupt, bankruptcy, and and leaves you hanging, and you know, you're spent a million plus dollars of your money, you know, trying to fund his projects that he's not paying for. So you overbill, try to compensate. And when he doesn't have the money to pay, it don't matter how much you overbill, if you don't get the money, it'll do any good. Yeah.
SPEAKER_03Which that that ties into the idea of making sure that you're not so dependent on a single source of income.
SPEAKER_01As my dad said, Oh, you know, that's where we messed up, was putting all of our eggs in one basket. Yeah.
SPEAKER_02Now, does your bond help you protect against that?
SPEAKER_01This is private work, so they had to be bonded.
SPEAKER_02Is there ever an opportunity where for private work you can bond it? Even
SPEAKER_01well, there is, but it's mostly on the GC or the owner. He may request a bond to make sure he's secured, but most of the time you as a contractor or subcontractor, you know, do you want to stay out of bonding as much as possible because extra cost?
SPEAKER_02It is, but you know, it's all you know, similar to insurance, right? I mean, where of course it's going to cost you more from your margin.
SPEAKER_01But
SPEAKER_02but if you were to be in some type of event where the person who's hired you goes bankrupt, like it could have a domino effect for all the subcontractors they've hired out. But if you happen to have insurance or bond to protect yourself in that situation, is that the right approach?
SPEAKER_01But you as the owner, me as a contractor, if you're not willing to request a bond or want a bond, then there's no way I could force you to do that. And so there's no benefit for me to have a bond against myself. And I can have a bond against you if you're not willing to bond the project.
SPEAKER_03Is there an insurance type of product that
SPEAKER_01it's a bond? That's it. That's your insurance.
SPEAKER_03But I'm saying that would protect you as a subcontractor.
SPEAKER_01You have a bid bond, which is initiated by the owner, and that's like if you default on your bid, it goes to the next lowest bidder, and then you've got to pay the difference. That's where your insurance company comes in. It's all insurance. And then you have a payment and performance bond. So if you award me the project and then I default after starting the project, then you as an owner are guaranteed that you're going to get your money, you're going to get a project, and whatever it costs you, in addition, my bond is going to pay for that. But me as a subcontractor, I can't really request a bond because that's going to cost me the job. You know, the owner's like, you know, I'm the one that has to be protected.
SPEAKER_03So there's nothing that works the opposite way that protects you from the GC going down.
SPEAKER_02So that's more maybe a word of caution as a subcontractor is if you have the opportunity, be selective on jobs that have bonds.
SPEAKER_01Yeah, and it's it's like, you know, anytime there's a bond share, you know, like a GC, maybe been a project and you're you're a subcontractor on that GPC GC, and they're going to ask you your bond rate. You know, whether it be, you know, 0.92% or 1.3%, whatever it may be, depending on the magnitude of the monetary amount, then if you include that in there, you know that you're a protected in that bond. And you know, the owner also is protecting that bond because you've paid X amount of dollars. But what it boils down to is like you as a GC, or I mean you as a sub, if you don't perform that bond that you've paid, only protects the owner, saying that, you know, hey, I can get someone else to come in, finish your work, and whatever it costs me extra, your bonding company is going to pay for it. So there's really not a whole lot of protection there for, you know, when someone says they're licensed and bonded, bonded means that I'm guaranteeing you if you hire me, if if I screw up or back out, you're gonna get your work done, whatever it costs you. My my insurance company's gonna pay the difference.
SPEAKER_03So, Jeff, that that was a big thing that got um your company in trouble years ago, your dependence on the single client. Looking back, what could you have done differently to somewhat mitigate that that risk from the single source of
SPEAKER_01well to be able to defer and say, you know, like I'm gonna bid work to you, but I've also got to focus on other clients. I've got to bid work to them as well. We did not do that. This one particular guy was giving us so much work, and it's like every time we gave him a bid, he'd call us like, you know, I want you to do this. I want you to do this. And we've got to where, you know, we had actually added more crews, we were subbing out more work, and we got to the point to where, you know, we did not have enough people, even with our subs, to do the work we had. I mean, you know, we we were we were doubling in size every year. Done that for eight years straight. Well, about six years straight.
SPEAKER_00And it's not like the GC you were working with said, you know, I'm gonna go file bankruptcy. I mean, that wasn't his plan either.
SPEAKER_01No, I'm no, I'm sure it wasn't.
SPEAKER_00Yeah, but he
SPEAKER_01he never gave us a heads up.
SPEAKER_00Right. No. He
SPEAKER_01kept giving us
SPEAKER_00working relationship.
SPEAKER_01We even got to the point to where, you know, if we we gave him an invoice for that month, he was paying like 30 to 50 percent of that invoice. And then he'd have excuses like, you know, hey, you know, I had to pay for this, I had to pay for that, I'm gonna catch you up on this next project or you know, later down the road. You know, we had so much work with him, like, well, okay. Yeah. Well, next month, same thing.
SPEAKER_00And it was good for a long time. So you had no reason to suspect that. Right.
SPEAKER_03But that that's another clue, then, if you're in that situation and suddenly payments are not turning out quite right. As crazy
SPEAKER_00there as they
SPEAKER_03could be a sign that there's trouble ahead. Exactly.
SPEAKER_02You look for patterns.
SPEAKER_00Yeah. Absolutely.
SPEAKER_01Yes.
SPEAKER_04Yeah.
SPEAKER_00Yeah. Well, that's good information, Jeff. I appreciate you sharing that with us. I hope it's a learning lesson for all of our viewers. Anyone like to leave us with some words of wisdom this evening?
SPEAKER_03I hear that, Frank. Cool.
SPEAKER_00And hope it's not the GC that's all in going live today.
SPEAKER_02GC's off train.
SPEAKER_00That's right. Well, thanks a lot, guys.
SPEAKER_01Yeah. You're
SPEAKER_00doing off the day. We'll see you next time.
SPEAKER_01See y'all.